We're still a few months off applying for a home loan for our first house, but just wondering how long it often takes from applying to moving in, considering a new land and new build, around Christchurch. We'll just imagine we already have land available in mind.

I'm sure it will vary absolutely wildly, but at the moment we don't know if it's usually a few moths, a year, or such.

Thanks!

Create new topic
3373 posts

Uber Geek
+1 received by user: 1874

Trusted
Lifetime subscriber

  Reply # 2063135 26-Jul-2018 18:59
Send private message quote this post

How long is a bit of string? Your question is sooooo open

 

John





Ex JohnR VodafoneNZ 17 years 4 days

3030 posts

Uber Geek
+1 received by user: 1505


  Reply # 2063144 26-Jul-2018 19:04
Send private message quote this post

12 - 18 months starting from scratch, but sooooo many variables.  Things always take longer and cost more than you think. Typical build for a family home based on my experience 14 - 18 weeks once you break ground.  Smaller simpler house less, larger more complicated home more.  Depends on trade availability as well.    





Always be yourself, unless you can be Batman, then always be the Batman



299 posts

Ultimate Geek
+1 received by user: 94


  Reply # 2063154 26-Jul-2018 19:18
Send private message quote this post

We are probably 3/4 of the way through from applying for a construction loan, purchasing land, to now having our house 2 months out from completion. From memory we started the whole application process mid Feb but we had all our ducks lined up from deposit to having land (titled) and house design all ready to go so it was mostly all contracts and lawyers up to the point the slab was poured.

 

We are building in the Christchurch region too, are you looking at house and land package or design and build? a few things can throw it out a bit longer like applying for a title and council permits.

 

The general consensus I got from most builders was a build time of 5-9 months weather permitting, currently our build is shaping up to come in just under or on 5 months with only one setback due to weather.  

 

 

 

 




255 posts

Ultimate Geek
+1 received by user: 37


  Reply # 2063198 26-Jul-2018 21:59
Send private message quote this post

Thanks very much for the replies :) Completely understand it being a how long is a piece of string question. There's an infinite number of different scenarios. But it does tell us it's not just a 3 month type of thing (which we didn't think it was, but wanted to check).

 

It'd be great if we could get all our ducks lined up late this year. I'm a student at the moment, ending this November, so I'm sure that will delay things if it takes a bit of time to get a job. I'm self employed in the meantime too though, although I bet that complicates things in terms of getting a loan approved too.

 

We're probably looking for a design and build, but it's one of those things we'll have to research a lot into. It might end up that all we can afford is a house and land package choosing one of their pre-made plans. That's good to know too though, that it will take a bit longer to get the title and permits.

 

Just under 5 months sounds like you did really well though yeah!


Mad Scientist
18706 posts

Uber Geek
+1 received by user: 2381

Trusted
Lifetime subscriber

  Reply # 2063199 26-Jul-2018 22:07
One person supports this post
Send private message quote this post

Buy land, Design & build in 3-5 months???

 

I was thinking more like minimum 12 months.


14215 posts

Uber Geek
+1 received by user: 1828


  Reply # 2063221 27-Jul-2018 00:55
Send private message quote this post

Best person to ask is the developer or whoever you are buying it from, as I am guessing it is a customised 'off the plan house', rather than architect designed for you. If it is an off the plan house, then the council consent process etc, should be faster, as they will likely be following plans that have been used before. 




255 posts

Ultimate Geek
+1 received by user: 37


  Reply # 2063317 27-Jul-2018 09:07
Send private message quote this post

More like minimum 12 months? It's looking like that yes. That's what I was hoping to get an idea on with the thread.

 

I'm absolutely certain we'll get a customised off the plan house rather than a architect, so that's good to know it won't delay things quite as much as it could otherwise.

 

 


4005 posts

Uber Geek
+1 received by user: 698

Trusted
Subscriber

  Reply # 2063568 27-Jul-2018 12:37
Send private message quote this post

Cookie cutter 'off the plans' purchases should be easy because you would typically pay an upfront deposit of only around 10% and then the balance on completion.

 

A project that you are managing yourself is more complicated because you are likely to need to draw down the mortgage to make progress payments to the builder.


Mad Scientist
18706 posts

Uber Geek
+1 received by user: 2381

Trusted
Lifetime subscriber

  Reply # 2063610 27-Jul-2018 12:51
Send private message quote this post

alasta:

 

Cookie cutter 'off the plans' purchases should be easy because you would typically pay an upfront deposit of only around 10% and then the balance on completion.

 

A project that you are managing yourself is more complicated because you are likely to need to draw down the mortgage to make progress payments to the builder.

 

 

Yes but you might not the on the top of their hitlist. Imagine 100 people wanting to build ... all want a house by Christmas. Then you need good weather, tradies, plumber to do their bit before electrician, council to sign off before the the gib can go on before the painter can before the ...

 

minumum 12 months.


2513 posts

Uber Geek
+1 received by user: 937

Subscriber

  Reply # 2063620 27-Jul-2018 13:03
Send private message quote this post

As others have said, tons of factors. We took 10 months from picking a location to moving in - so that was finance, picking & buying a lot, plans & consents, build, move-in. But it was a pretty ready-to-go site - so not a lot of earthworks, and a single-story building, both of which helped with timeframes.





Windows 7 x64 // i5-3570K // 16GB DDR3-1600 // GTX660Ti 2GB // Samsung 830 120GB SSD // OCZ Agility4 120GB SSD // Samsung U28D590D @ 3840x2160 & Asus PB278Q @ 2560x1440
Samsung Galaxy S5 SM-G900I w/Spark

738 posts

Ultimate Geek
+1 received by user: 236

Trusted
Subscriber

  Reply # 2063629 27-Jul-2018 13:31
Send private message quote this post

Here are the timelines for our land purchase/new house build:

 

 

 

1. Start: Jan 2012 "Window Shopping"

 

2. Land Purchase: Nov 2012 - existing section, title available immediately, but we deferred 

 

3. Builder selection starts: Nov 2012

 

4. Builder/Designer chosen: Feb 2013

 

5. Plans agreed/costed: June 2013

 

6. Bank Finance arrangement: June 2013

 

7. Settlement on Land (i.e. Loan drawn initially): Sept 2013

 

8. Construction begins: end Sept/Early Oct 2013

 

9. Moving into completed house: April 2014.

 

 


596 posts

Ultimate Geek
+1 received by user: 100


  Reply # 2063930 28-Jul-2018 09:58
Send private message quote this post

However long it should take, say 1 year, double it.

 

There will be delays, problems, stuffups and so on.

 

better to just buy a house.




255 posts

Ultimate Geek
+1 received by user: 37


  Reply # 2063932 28-Jul-2018 10:05
Send private message quote this post

Paying just 10% at the beginning and the balance later certainly has its advantages yes.

 

Thanks everyone, this gives us a much more realistic idea of what to expect. Ideally we'll have time to get started before I finish studying :)

 

 


4784 posts

Uber Geek
+1 received by user: 1932


  Reply # 2064871 30-Jul-2018 11:13
Send private message quote this post

Home loan these days is usually the fastest part of buying a house.





Mike

Create new topic

Twitter »

Follow us to receive Twitter updates when new discussions are posted in our forums:



Follow us to receive Twitter updates when news items and blogs are posted in our frontpage:



Follow us to receive Twitter updates when tech item prices are listed in our price comparison site:





News »

Intel introduces new NUC kits and NUC mini PCs
Posted 16-Aug-2018 11:03


The Warehouse leaps into the AI future with Google
Posted 15-Aug-2018 17:56


Targus set sights on enterprise and consumer growth in New Zealand
Posted 13-Aug-2018 13:47


Huawei to distribute nova 3i in New Zealand
Posted 9-Aug-2018 16:23


Home robot Vector to be available in New Zealand stores
Posted 9-Aug-2018 14:47


Panasonic announces new 2018 OLED TV line up
Posted 7-Aug-2018 16:38


Kordia completes first live 4K TV broadcast
Posted 1-Aug-2018 13:00


Schools get safer and smarter internet with Managed Network Upgrade
Posted 30-Jul-2018 20:01


DNC wants a safer .nz in the coming year
Posted 26-Jul-2018 16:08


Auldhouse becomes an AWS Authorised Training Delivery Partner in New Zealand
Posted 26-Jul-2018 15:55


Rakuten Kobo launches Kobo Clara HD entry level reader
Posted 26-Jul-2018 15:44


Kiwi team reaches semi-finals at the Microsoft Imagine Cup
Posted 26-Jul-2018 15:38


KidsCan App to Help Kiwi Children in Need
Posted 26-Jul-2018 15:32


FUJIFILM announces new high-performance lenses
Posted 24-Jul-2018 14:57


New FUJIFILM XF10 introduces square mode for Instagram sharing
Posted 24-Jul-2018 14:44



Geekzone Live »

Try automatic live updates from Geekzone directly in your browser, without refreshing the page, with Geekzone Live now.



Are you subscribed to our RSS feed? You can download the latest headlines and summaries from our stories directly to your computer or smartphone by using a feed reader.

Alternatively, you can receive a daily email with Geekzone updates.