Topic # 222950 5-Sep-2017 11:27
Send private message quote this post

Hoping someone can offer some advice.

 

My mother moved into a newly built house on a sub-divided section in Enable fibre area a few weeks ago.

 

Checking Chorus and Enable websites and calling Spark about a new connection revealed that the properly was listed as having no copper or fibre available.

 

Spoke to the developer who confirmed that there was Enable approved ducting already laid from the street to exterior of the house which I have confirmed.

 

Checking Enables website again showed that 3A, 3B and 3C all showed as fibre available but 3D (where my mother is) did not.

 

On 21st Aug I submitted an address check query to Enable via their website.

 

On 24th Aug I contacted Spark and they said their address management team would also contact Enable.

 

On 25th Aug Enable emailed me with a map showing the house numbering in their system. The error was that 3D was recorded as No. 3 in their system. I emailed Enable back with the correction.

 

On 31st Aug Enable confirmed "address is now available to the service providers to use to send us a fibre order" and I have confirmed it on their website.

 

On 3rd Aug I emailed the guy I've been dealing with at Spark about the Enable email and the answer was that Spark's address management teams are still waiting on an update from Enable.

 

I'm worried I have confused the process by logging a job with Enable at the same time Spark did.

 

Is there anyway to expedite this process or do I just have to wait for the process to run it's course.


Filter this topic showing only the reply marked as answer Create new topic
672 posts

Ultimate Geek
+1 received by user: 514

Trusted
Spark NZ

  Reply # 1858925 5-Sep-2017 13:12
5 people support this post
Send private message quote this post

Flick me a private message with the full address details and I will look into it for you. It shouldn't be a drama to sort out at all.





The views expressed by me are not necessarily those of my employer Spark NZ Ltd



182 posts

Master Geek
+1 received by user: 58


  Reply # 1859488 6-Sep-2017 09:52
Send private message quote this post

Thanks, PM sent.


 
 
 
 


672 posts

Ultimate Geek
+1 received by user: 514

Trusted
Spark NZ

  Reply # 1860185 7-Sep-2017 10:32
One person supports this post
Send private message quote this post

All sorted. You should be able to order now cool





The views expressed by me are not necessarily those of my employer Spark NZ Ltd



182 posts

Master Geek
+1 received by user: 58


  Reply # 1860284 7-Sep-2017 12:53
Send private message quote this post

Order is now placed, thank you so much.

 

It's great to have some progress.

 

Now just to wait for Enable to arrange appointments for scoping and install.




182 posts

Master Geek
+1 received by user: 58


  Reply # 1866531 14-Sep-2017 21:20
One person supports this post
Send private message quote this post

Just a quick followup.

 

We had more complications because Enable's system decided consent was required even though the house was a new build that they had already installed the lead-in for.

 

Once we corrected that we went from booking -> scoping -> install in three working days which is fantastic. Fibre was connected and working at midday today.

 

Almost everyone I've dealt with at Spark and Enable have been very helpful and I've been very impressed.

 

It's just a pity that the initial incorrect information in Enable's systems turned what could have been 3 day turnaround into a 3 week drama followed by a three day turnaround.


6 posts

Wannabe Geek


  Reply # 1866556 14-Sep-2017 23:09
Send private message quote this post

Nice one, wish my Fibre install (at a new house build) went that smoothly.

 

Our new build is at the bottom of a shared driveway (with 2 other houses and 1 empty section).  For some reason when fibre was put in place for the 2 other houses someone didn't take it all the way to the final two sections (one of which is now mine).

 

So now awaiting for consents from the neighbours (2 houses are easy, empty section is owned by someone in North Island that may be missing).

 

Think they were allowing 30 days to obtain the consents, which is about to expire next week, at which point the order is canceled and i believe i go into a stand down queue for 6 months i was told. 

 

However will admit that talking to the people from Spark and Chorus they have been most helpful and courteous where possible, just the paperwork (or lack there of) that is getting in my way.   Being a new build i've been told there is no copper either so i can't even get standard ADSL hooked up.


6798 posts

Uber Geek
+1 received by user: 2164

Subscriber

  Reply # 1866584 15-Sep-2017 06:21
One person supports this post
Send private message quote this post

@Surago once the new rules come in in october, you may be able to apply again and if its an easy install then the absent neighbour has 14 days i think to decline it, if no answer is heard then implied consent is given so hopefully this can work in your favour.


6 posts

Wannabe Geek


  Reply # 1866795 15-Sep-2017 12:01
Send private message quote this post

Oh sweet, hopefully that will help then.  Did find a blog post from chorus mentioned the 1st of October for rule changes.

 

 

 

Also a quick follow up i believe if i reapply with the same reference number that'll avoid the 6 month stand down too.  So fingers crossed.


Filter this topic showing only the reply marked as answer Create new topic



Twitter »

Follow us to receive Twitter updates when new discussions are posted in our forums:



Follow us to receive Twitter updates when news items and blogs are posted in our frontpage:



Follow us to receive Twitter updates when tech item prices are listed in our price comparison site:





News »

FUJIFILM introduces X-E3 mirrorless camera with wireless connectivity
Posted 18-Sep-2017 13:53


Vodafone announces new plans with bigger data bundles
Posted 15-Sep-2017 10:51


Skinny launches phone with support for te reo Maori
Posted 14-Sep-2017 08:39


If Vodafone dropping mail worries you, you’re doing online wrong
Posted 11-Sep-2017 13:54


Vodafone New Zealand deploy live 400 gigabit system
Posted 11-Sep-2017 11:07


OPPO camera phones now available at PB Tech
Posted 11-Sep-2017 09:56


Norton Wi-Fi Privacy — Easy, flawed VPN
Posted 11-Sep-2017 09:48


Lenovo reveals new ThinkPad A Series
Posted 8-Sep-2017 14:37


Huawei passes Apple for the first time to capture the second spot globally
Posted 8-Sep-2017 10:45


Vodafone initiative enhances te reo Maori pronunciation on Google Maps
Posted 8-Sep-2017 10:40


Voyager Internet expand local internet phone services company with Conversant acquisition
Posted 6-Sep-2017 18:27


NOW Expands in to Tauranga
Posted 5-Sep-2017 18:16


Windows 10 Fall Creators Update coming Oct. 17
Posted 4-Sep-2017 14:10


Garmin introduce Garmin vivoactive 3
Posted 1-Sep-2017 18:38


Kiwibank wastes $90 million on software – Reseller News
Posted 1-Sep-2017 13:45



Geekzone Live »

Try automatic live updates from Geekzone directly in your browser, without refreshing the page, with Geekzone Live now.



Are you subscribed to our RSS feed? You can download the latest headlines and summaries from our stories directly to your computer or smartphone by using a feed reader.

Alternatively, you can receive a daily email with Geekzone updates.