I just have to put this here. From my protesting youth that still remains, thank you John Hanlon

 

Leaf falls to kiss the image of a mountain 
the early morning mist has ceased to play 
Birds dancing lightly on the branches by a fountain 
Of waterfall which dazzles with its spray 
Tall and strong and aged, contented and serene 
The Kauri tree surveys this grand domain
For miles and miles around him, a sea of rolling green 
Tomorrow all this  beauty won't remain 

 

  Damn the dam cried the fantail, 
  As he  flew into as he  flew into the sky, 
  To give  power to the  people 
  All this  beauty has to die 

 

Rain falls from above and splashes on the ground 
Goes running down the mountain to the sea 
And leaping over pebbles makes such a joyful sound 
Such as Mother Nature's meant to be

 

I have grave reflection, reflection of a grave
Trees that once lived green now dead and brown
The homes of tiny animals and little birds as well
For the sake of man's progression have been drowned 

 

  Damn the dam cried the fantail, 
  As he flew into as he flew into the sky, 
  To give power to the people 
  All this beauty has to die 

 

 

 

  Damn the dam cried the fantail, 
  As he flew into as he flew into the sky,

 

  Damn the dam cried the fantail, 
  As he flew into as he flew into the sky, 
  To give power to the people 
  All this beauty has to die... 





Mike
Retired IT Manager. 
The views stated in my posts are my personal views and not that of any other organisation.

 

There is no planet B

 

 


9011 posts

Uber Geek


  # 2342927 24-Oct-2019 11:12
One person supports this post
Send private message quote this post

afe66: Is nz made aluminium affected by trump aluminium tariffs ?

 

Yes.

 

It's also a good example of a Trump own-goal, as some very high purity NZAS aluminium grades that can't be supplied by US smelters are exported to the US.

 

But it's not a huge volume, google tells me about $25 million exports to the US per annum.


 
 
 
 


377 posts

Ultimate Geek


  # 2342933 24-Oct-2019 11:31
One person supports this post
Send private message quote this post

Geektastic:

 

Who else should pay?

 

 

 

 

Obviously it should be split fairly across to the end user, so users closer to the power station pay less than people situated at a distance.

 

 

 

Geektastic:

 

Obviously capital expenditure needs to be charged over a phased period rather than all at once. However, I do not mind paying for a service worth paying for. At the moment, I see more power cuts annually than I ever have in my life, so at the moment I am paying for service not worth paying for.

 

 

 

 

That is your argument with your transmission company, mine is what am I (and NZAS) making your poor supply cheaper than it should be?


4243 posts

Uber Geek


  # 2342935 24-Oct-2019 11:35
One person supports this post
Send private message quote this post

JimmyH:

 

If Meridian and Rio Tinto, negotiating on a purely commercial basis without Ministerial interference,  can agree a contract that suits them both and the Smelter stays open, then that's fine with me. If they can't and the Smelter closes, then that's also fine by me. The Smelter should live or die on it's economics. What it shouldn't do is live based on special pleading and taxpayer cash.

 

 

As has been mentioned is a bunch of other post, its not the Meridian deal that is the key issue in this

 

its the price Transpower ( a 100% owned government monopoly) charges, and the Grid charging mechanism regulated (under government rules) by the Electricity Authority (EA) and the Commerce Commission,

 

Tiwai is getting overcharged,  but when the EA proposed a pricing model in 2016 that would saving them $20 million a year, ( and increase domestic prices from $50/100 a year,) all hell broke loose

 

https://www.interest.co.nz/news/81632/electricity-authority-proposal-new-transmission-pricing-system-would-raise-power-bills

 

its new proposal that they are currently consulting on is a ~11 million saving from 2024, and Tiwai have said ( IMHO rightfully) that doesn't cut it..

 

 

 

 


611 posts

Ultimate Geek


  # 2342945 24-Oct-2019 11:58
Send private message quote this post

The plant will close some day. The implications of the closure will hit, some day. It’s “do I take my medicine today, or tomorrow?”.

 

I would make Rio Tinto work it until they no longer want to, but without subsidy, and when they give the 12 months notice, act. It might be good to do the grid update anyway - that 600MW will become available some day.

 

 





BlinkyBill


2205 posts

Uber Geek

Lifetime subscriber

  # 2343003 24-Oct-2019 13:23
Send private message quote this post

This issue was one of reasons I didnt buy meridian shares

13725 posts

Uber Geek

Trusted
Lifetime subscriber

  # 2343034 24-Oct-2019 14:21
Send private message quote this post

jfanning:

Geektastic:


Who else should pay?



 


Obviously it should be split fairly across to the end user, so users closer to the power station pay less than people situated at a distance.


 


Geektastic:


Obviously capital expenditure needs to be charged over a phased period rather than all at once. However, I do not mind paying for a service worth paying for. At the moment, I see more power cuts annually than I ever have in my life, so at the moment I am paying for service not worth paying for.



 


That is your argument with your transmission company, mine is what am I (and NZAS) making your poor supply cheaper than it should be?



As I said, I don't mind paying for a quality service. Our bill is probably $3000 a year or so as it is.

If paying more guaranteed service, then within reason no complaints from me.





 
 
 
 


4243 posts

Uber Geek


  # 2343044 24-Oct-2019 14:40
One person supports this post
Send private message quote this post

Geektastic:
As I said, I don't mind paying for a quality service. Our bill is probably $3000 a year or so as it is.

If paying more guaranteed service, then within reason no complaints from me.

 

Most of the faults you are experiencing are local network outages,

 

This is not what is being talked about.....

 

if you whole town looses power, that's likely a Transpower grid issue. and where the increased charges come from.

 

Auckland has had a number of grid faults over the last 10-15 years (they tend to make the news) and T/power has spent some significant $$$ upgrading equipment and lines to make sure it doesn't happen again.... 


73 posts

Master Geek


  # 2343047 24-Oct-2019 14:48
Send private message quote this post

wellygary:

 

As has been mentioned is a bunch of other post, its not the Meridian deal that is the key issue in this

 

its the price Transpower ( a 100% owned government monopoly) charges, and the Grid charging mechanism regulated (under government rules) by the Electricity Authority (EA) and the Commerce Commission,

 

Tiwai is getting overcharged,  but when the EA proposed a pricing model in 2016 that would saving them $20 million a year, ( and increase domestic prices from $50/100 a year,) all hell broke loose

 

https://www.interest.co.nz/news/81632/electricity-authority-proposal-new-transmission-pricing-system-would-raise-power-bills

 

its new proposal that they are currently consulting on is a ~11 million saving from 2024, and Tiwai have said ( IMHO rightfully) that doesn't cut it..

 

 

The old method allocated transmission costs based on the amount of power used. 

 

The new proposal works (in simple terms) by spreading the investment costs of the network (e.g. HVDC upgrades) across the parties who benefit.  So if a party gets 10% of the benefit from the HVDC upgrades, they pay 10% of the HVDC investment cost.  If a party doesn't benefit from an upgrade they don't pay, for example Tiwai gets very little benefit from the North Island Grid Upgrade projects and as such doesn't pay much.

 

So I'm not sure Tiwai have a strong case around the 11 million saving not being good enough, they are paying their share of the projects that they benefit from.


73 posts

Master Geek


  # 2343051 24-Oct-2019 14:53
One person supports this post
Send private message quote this post

tehgerbil:

 

Honestly Tiwai point is a disgusting blight on our energy industry. The sweetheart arrangement is appalling and the only winners are the shareholders for Tiwai and Meridian.

 

 

Not true.  Tiwai is hugely beneficial to the NZ electrical system as a whole because it effectively offers demand response.  When the power system gets in trouble Tiwai will pause some lines, effectively dumping demand out of the system and letting the system get back on track.  This is a massive upside.


1154 posts

Uber Geek


  # 2343066 24-Oct-2019 15:26
Send private message quote this post

Tiwai to the best of my understanding is not connected to the grid, it's connected directly and is the sole consumer of a power station





Most problems are the result of previous solutions...

All comment's I make are my own personal opinion and do not in any way, shape or form reflect the views of current or former employers unless specifically stated 



18715 posts

Uber Geek

Trusted

  # 2343068 24-Oct-2019 15:32
Send private message quote this post

Beccara:

 

Tiwai to the best of my understanding is not connected to the grid, it's connected directly and is the sole consumer of a power station

 

 

Thats what Handle said, and costly to connect to the grid also. IIRC it was going to be a private generator (Manapouri), but Govt built it instead for them, so the transmission fees they pay is in fact unfair as they are off grid, not part of NZ's power system. Interesting stuff


302 posts

Ultimate Geek


  # 2343109 24-Oct-2019 15:51
Send private message quote this post

Tiwai has what is effectively a private (albeit owned and operated by Transpower) connection to Matapouri. Matapouri is also connected to the general grid, therefore if the general grid needs more juice, Tiwai closes somes lines giving back capacity to Matapouri so it can in turn pump more into the general grid.


1111 posts

Uber Geek


  # 2343110 24-Oct-2019 15:52
2 people support this post
Send private message quote this post

That isn't entirely correct. There is a physical connection but it is constrained.

 

The Transpower maps are not working at the moment otherwise I would link them, but in a nut-shell the power-lines between Invercargill and the national grid are skinnier than the lines between Invercargill and Manapouri. 

 

The gird is configured to supply only sufficient to meet Invercargills peak demand, and is not able to carry the full output of Manapouri north. When Manapouri is dumping excess capacity into the grid, it is running Invercargill and then the lines into invercargill are freed up to carry that much power again north. In greatly simplified terms Manapouri can only export 2x Invercargills peak requirements to the gird. This still doesn't equate to the full output of Manapouri. 

 

Edit: This map is back up: https://www.transpower.co.nz/sites/default/files/plain-page/attachments/Transmission-map-south-island0718.pdf

 

found on this page: https://www.transpower.co.nz/keeping-you-connected/maps-and-gis-data-0


302 posts

Ultimate Geek


  # 2343112 24-Oct-2019 15:58
Send private message quote this post

Nothing I said was incorrect. Just very simplified :) 


1 | 2 | 3 | 4 | 5
View this topic in a long page with up to 500 replies per page Create new topic



Twitter and LinkedIn »



Follow us to receive Twitter updates when new discussions are posted in our forums:



Follow us to receive Twitter updates when news items and blogs are posted in our frontpage:



Follow us to receive Twitter updates when tech item prices are listed in our price comparison site:





News »

Vodafone integrates eSIM into device and wearable roadmap
Posted 17-Jan-2020 09:45


Do you need this camera app? Group investigates privacy implications
Posted 16-Jan-2020 03:30


JBL launches headphones range designed for gaming
Posted 13-Jan-2020 09:59


Withings introduces ScanWatch wearable combining ECG and sleep apnea detection
Posted 9-Jan-2020 18:34


NZ Police releases public app
Posted 8-Jan-2020 11:43


Suunto 7 combine sports and smart features on new smartwatch generation
Posted 7-Jan-2020 16:06


Intel brings innovation with technology spanning the cloud, network, edge and PC
Posted 7-Jan-2020 15:54


AMD announces high performance desktop and ultrathin laptop processors
Posted 7-Jan-2020 15:42


AMD unveils four new desktop and mobile GPUs including AMD Radeon RX 5600
Posted 7-Jan-2020 15:32


Consolidation in video streaming market with Spark selling Lightbox to Sky
Posted 19-Dec-2019 09:09


Intel introduces cryogenic control chip to enable quantum computers
Posted 10-Dec-2019 21:32


Vodafone 5G service live in four cities
Posted 10-Dec-2019 08:30


Samsung Galaxy Fold now available in New Zealand
Posted 6-Dec-2019 00:01


NZ company oDocs awarded US$ 100,000 Dubai World Expo grant
Posted 5-Dec-2019 16:00


New Zealand Rugby Selects AWS-Powered Analytics for Deeper Game Insights
Posted 5-Dec-2019 11:33



Geekzone Live »

Try automatic live updates from Geekzone directly in your browser, without refreshing the page, with Geekzone Live now.


Support Geekzone »

Our community of supporters help make Geekzone possible. Click the button below to join them.

Support Geezone on PressPatron



Are you subscribed to our RSS feed? You can download the latest headlines and summaries from our stories directly to your computer or smartphone by using a feed reader.

Alternatively, you can receive a daily email with Geekzone updates.