# 138021 17-Dec-2013 10:24
Send private message

I have the nice people from CSR/Visionstream/Chorus rolling out ducting in our street and surrounding area at the moment. Most of the ducting seems to be in place and they're starting to fill in the holes, connect the junction boxes, cabinet etc.

I just checked the chorus map and our cabinet area has gone from March 2014 to April 2014. Being that in another couple of weeks all the ducting will be in, why does it take 3 months for it to be available to consumers? I would think that the ducting would take the longest time.

View this topic in a long page with up to 500 replies per page Create new topic
 1 | 2
1051 posts

Uber Geek
+1 received by user: 207


  # 953559 17-Dec-2013 10:27
Send private message

Jointing, If it's anything like some other LFC's the Jointing is the longest part as it requires tools and skills the (cheaper) ducting guys just dont have




Most problems are the result of previous solutions...

All comment's I make are my own personal opinion and do not in any way, shape or form reflect the views of current or former employers unless specifically stated 

2534 posts

Uber Geek
+1 received by user: 943

Subscriber

  # 953599 17-Dec-2013 11:17
Send private message

Yeah, they finished the ducting, refilled holes etc outside our place a few weeks ago, but Chorus site says May expected date lol. Oh well. It used to say March.

 
 
 
 


134 posts

Master Geek
+1 received by user: 37


  # 953657 17-Dec-2013 12:24
One person supports this post
Send private message

Once the ducts are in and tested, they need to feed the fibre through the ducts to the cabinet from the telephone exchange. There is the splicing as mentioned above and testing to do plus time for the quality control people to do their stuff. A lot of the testing is between the telephone exchange and thecabient so you don't see much of it happening when standing on the street and it takes a while.

457 posts

Ultimate Geek
+1 received by user: 28

Trusted

  # 953842 17-Dec-2013 17:05
Send private message

Your street may be the first of the area, Also this is the Xmas period and Chorus is in Brown out very soon....
Xmas time always seems to delay any project that follows on into the new year.




---------------------------------------------------------------
Nebukadnessar


6549 posts

Uber Geek
+1 received by user: 1273

Trusted
Lifetime subscriber

  # 953844 17-Dec-2013 17:08
Send private message

At least Chorus is updating the map in your area; the data for Whakatane hasn't changed since early October despite work happening all over the place!

307 posts

Ultimate Geek
+1 received by user: 3


  # 953973 17-Dec-2013 22:35
Send private message

as above ... what you are seeing with the ducting going down the street is barely scratching the surface of what is actually required for the area to be available for install.

maybe 50% of the total work if that? depending on how you look at it.




Disclaimer: Comments I make are NOT on behalf of my employer, these comments are mine and mine alone.

14744 posts

Uber Geek
+1 received by user: 2745

Trusted
Subscriber

  # 954025 18-Dec-2013 07:20
Send private message

I think it's best to assume any UFB install will take a year from the date it's requested. That way you may be pleasently surprised when it happens in only 3 or 6 months.

2822 posts

Uber Geek
+1 received by user: 752


  # 954482 18-Dec-2013 20:01
Send private message

they have been digging for the last week down my street to lay fibre and this morning they managed to cut the phone cable to the street resulting in 4 hours of no internet or phone. The only good thing is that after fixing it my sync rate went up 2-3000 . does not bode well for rest of installation.




Common sense is not as common as you think.


1991 posts

Uber Geek
+1 received by user: 133

Trusted

  # 955858 21-Dec-2013 15:01
Send private message

The ducting is one of the first parts of the job!




Qualified in business, certified in fibre, stuck in copper, have to keep going  ^_^

552 posts

Ultimate Geek
+1 received by user: 83

Trusted
Lifetime subscriber

  # 955861 21-Dec-2013 15:12
Send private message

Noodles: I have the nice people from CSR/Visionstream/Chorus rolling out ducting in our street and surrounding area at the moment. Most of the ducting seems to be in place and they're starting to fill in the holes, connect the junction boxes, cabinet etc.

I just checked the chorus map and our cabinet area has gone from March 2014 to April 2014. Being that in another couple of weeks all the ducting will be in, why does it take 3 months for it to be available to consumers? I would think that the ducting would take the longest time.


Ha, at least you have an indication of an install. The SAT map for me still says "UFB deployment dates for your area are still being developed" even though some friends down the street( less than 500 meters away) have had the card in the letterbox and have had the ducting put in.
I must be on the wrong side of the local shops :-(

113 posts

Master Geek
+1 received by user: 28

Subscriber

  # 959714 31-Dec-2013 20:19
Send private message

Noodles: I have the nice people from CSR/Visionstream/Chorus rolling out ducting in our street and surrounding area at the moment. Most of the ducting seems to be in place and they're starting to fill in the holes, connect the junction boxes, cabinet etc.

I just checked the chorus map and our cabinet area has gone from March 2014 to April 2014. Being that in another couple of weeks all the ducting will be in, why does it take 3 months for it to be available to consumers? I would think that the ducting would take the longest time.


For what it's worth, the ducting was installed outside our house in December last year, and I wasn't able to connect until March...3-4 months seems pretty typical around here (Chorus area)



468 posts

Ultimate Geek
+1 received by user: 84


  # 999223 5-Mar-2014 08:30
Send private message

Argh, just re-checked the Chorus maps and Apr 2014 has slipped until June 2014. Ducting was finished in January, Chorus guys have run the fibre backhaul (AFAIK) and have been working on the cabinet for the last 4 weeks.

Who's the best to contact about this? My ISP? Visionstream? Chorus?

1254 posts

Uber Geek
+1 received by user: 533


  # 999231 5-Mar-2014 08:42
One person supports this post
Send private message

I would't complain too much if I were you - at least you have work going on and a target date in the foreseeable future.  I'm like ubernoob: "UFB deployment dates for your area are still being developed" with no sign of activity in my neighbourhood yet - and I live less than 10 minutes (walking) from the heart of Lower Hutt city, so not exactly a remote area.

165 posts

Master Geek
+1 received by user: 54


  # 999277 5-Mar-2014 10:04
Send private message

andrew027: I would't complain too much if I were you - at least you have work going on and a target date in the foreseeable future.  I'm like ubernoob: "UFB deployment dates for your area are still being developed" with no sign of activity in my neighbourhood yet - and I live less than 10 minutes (walking) from the heart of Lower Hutt city, so not exactly a remote area.


Ditto, and I'm sure your not congested like me on the graph below;


Banana?
4712 posts

Uber Geek
+1 received by user: 1201

Subscriber

  # 999318 5-Mar-2014 10:44
Send private message

Oooh, just checked my address, and it has gone from June 2015 to 'between July 2014 and June 2015'. Different, but the same I expect.

 1 | 2
View this topic in a long page with up to 500 replies per page Create new topic



Twitter »

Follow us to receive Twitter updates when new discussions are posted in our forums:



Follow us to receive Twitter updates when news items and blogs are posted in our frontpage:



Follow us to receive Twitter updates when tech item prices are listed in our price comparison site:





News »

Techweek starting around NZ today
Posted 20-May-2019 09:52


Porirua City Council first to adopt new council software solution Datascape
Posted 15-May-2019 12:00


New survey provides insight into schools' technology challenges and plans
Posted 15-May-2019 09:30


Apple Music now available on Alexa devices in Australia and New Zealand
Posted 15-May-2019 09:11


Make a stand against cyberbullying this Pink Shirt Day
Posted 14-May-2019 20:23


Samsung first TV manufacturer to launch the Apple TV App and Airplay 2
Posted 14-May-2019 20:11


Vodafone New Zealand sold
Posted 14-May-2019 07:25


Kordia boosts cloud performance with locally-hosted Microsoft Azure ExpressRoute
Posted 8-May-2019 10:25


Microsoft Azure ExpressRoute in New Zealand opens up faster, more secure internet for Kiwi businesses
Posted 8-May-2019 09:39


Vocus Communications to deliver Microsoft Azure Cloud Solutions through Azure ExpressRoute
Posted 8-May-2019 09:25


Independent NZ feature film #statusPending to premiere during WLG-X
Posted 6-May-2019 22:13


The ultimate dog photoshoot with Nokia 9 PureView #ForgottenDogsofInstagram
Posted 6-May-2019 09:41


Nokia 9 PureView available in New Zealand
Posted 6-May-2019 09:06


Motorola Solutions joins local partners to deliver advanced communications network in New Zealand
Posted 30-Apr-2019 21:50


Micron launches high-performance NVMe SSDs for cloud and enterprise markets
Posted 30-Apr-2019 10:27



Geekzone Live »

Try automatic live updates from Geekzone directly in your browser, without refreshing the page, with Geekzone Live now.


Support Geekzone »

Our community of supporters help make Geekzone possible. Click the button below to join them.

Support Geezone on PressPatron



Are you subscribed to our RSS feed? You can download the latest headlines and summaries from our stories directly to your computer or smartphone by using a feed reader.

Alternatively, you can receive a daily email with Geekzone updates.