One person supports this post
Send private message

So, last week I thought, what the heck, time to go to UFB....

 

 

 

Placed order through my ISP, so far so good..

 

Two days later got call from Chorus saying site inspection planned for today, that was quick I thought, cool.... that was delayed to Monday at 6ish last night, okay I thought, I can work with that, (was advised that delay was due to not enough tech's being available, not totally happy, but okay, whats couple of days).  Install was re booked for the 9th Dec.  So far so good....

 

Then just now get a call from VisionStream saying that due to Chorus dumping Downer and awarding the contract to VisionStream, they now can't do my install until 2nd February 2017, as they need to relocate tech's from Auckland to Dunedin!!!!

 

Now I'm okay with Chorus awarding the contract to whomever the want, but seriously no installs to Feb, and I suspect that this date will move, I just have little confidence it won't.

 

Come on Chorus, you should have managed the transition better then this and ensured Dunedin wasn't left with long delays like this!

 

So if you are in Dunedin, be prepared for a long wait for UFB.  So much for Gigatown....

 

 

 

Grumpy rant over :-)

 

 

 

 

 

  


View this topic in a long page with up to 500 replies per page Create new topic
 1 | 2
522 posts

Ultimate Geek
+1 received by user: 115


  Reply # 1680784 1-Dec-2016 16:31
Send private message

Chorus called me yesterday and confirmed my site inspection and install date so hopefully it doesn't change..


898 posts

Ultimate Geek
+1 received by user: 786

Trusted
Chorus

  Reply # 1680976 1-Dec-2016 23:08
Send private message

You also have to remember that we are entering the busiest time of the year for LFCs and their technicians. There is a shortage of tech appointments all over the country for December and January (I know - I book them every day). Most of Auckland has no techs available for new installs until mid January now, and that is purely because the period when people have time to be home for installs wthout taking time off work (the Xmas/New Year holidays) is also the period when some techs all want to be on holiday too.

 

I am not saying you are not correct - but I am saying even if Chorus had not changed service companies, I believe there would still be a wait for an installation appointment at this time of year in most areas.





The views expressed by me are not necessarily those of my employer Chorus NZ Ltd


 
 
 
 


522 posts

Ultimate Geek
+1 received by user: 115


  Reply # 1681596 3-Dec-2016 10:00
Send private message

So for me, chorus have looked at my install and decided to proceed with the install today on inspection day instead of on the 12th! A great result considering UFB was ordered late Monday (28th) night

He mentioned they have had to delay a bunch of installs that cross in the path of power lines and don't come off a direct pole so I assume you have been affected by this :(


2219 posts

Uber Geek
+1 received by user: 684

Subscriber

  Reply # 1681616 3-Dec-2016 10:37
Send private message

Yeah there is a big debacle going on in Dunedin with power poles at the moment. Is it an over head install?




93 posts

Master Geek
+1 received by user: 5


  Reply # 1681627 3-Dec-2016 11:08
Send private message

skewt, pleased yours went ahead.

 

 

 

With regards to install, would have to be one of the easier ones, all underground and easy access from the roadside to the house, not over head, but I guess they wont know any of that until next year.

 

 

 

The biggest issue is the mucking around, as I suspect Chorus/Downer/VoiceStream would all have known what was happening with Dunedin installs, to be told one thing, then another, then another is where I have a problem....

 

 

 

 


919 posts

Ultimate Geek
+1 received by user: 224

Subscriber

  Reply # 1681641 3-Dec-2016 11:29
Send private message

I had my install (in Dunedin) done in late October after a 60 day wait, when I was talking to the Downer tech he said the wait was then around 80 days and that around 2-3 technicians were quitting each week at Downer as the contract with Chorus came to an end. 

 

He was also saying that a lot of installs were being delayed if they had to use Delta poles as a lot of them are red tagged.


522 posts

Ultimate Geek
+1 received by user: 115


  Reply # 1681675 3-Dec-2016 11:53
Send private message

I did notice the guy who installed my UFB today had a "VisionStream" sticker on his van.

 

 

 

 




93 posts

Master Geek
+1 received by user: 5


  Reply # 1682466 5-Dec-2016 13:18
Send private message

and an update, and lets call it the power of social media, and that someone from Chorus saw my post and thought, hell we can't let that happen.... :-)

 

 

 

but, get a phone call at midday, from Chorus, asking was I home, no, why, well we are booked to do your site inspection, so rather then say, hold it, its been rebooked for February, I said, give me 30min and I'll be there....  I get there, we have a chat for 10min about the how and what, I sign a few electronic forms and I ask so when are you going to do the actual install, he looks at me with a somewhat confused expression and says now....  so now I have two tech's here installing fibre.....

 

So I wonder what they will do in Feb :-)

 

 

 

 

 

 

 

 

 

 

 

 


Mad Scientist
19823 posts

Uber Geek
+1 received by user: 2681

Trusted
Lifetime subscriber

  Reply # 1682478 5-Dec-2016 13:26
Send private message

Oops. Maybe you can have a second connection :)))




Swype on iOS is detrimental to accurate typing. Apologies in advance.


448 posts

Ultimate Geek
+1 received by user: 168

Subscriber

  Reply # 1682510 5-Dec-2016 13:58
Send private message

Got a txt from Chorus today informing me my 12th December install has now been rescheduled for 3rd February. wtf

 

I'm out of town for nearly all of February so I guess if I try and reschedule this new appointment I'll be put off until April.

 

My install was scoped 3 weeks ago, and at the time the guy who turned up re confirmed installation would still be the 12th, so Its not like Chorus didn't know the Job was coming up. Its not even a difficult install

 

At this point I'm peed off enough, that I'm very close to cancelling the whole fiber install.

 

 


1514 posts

Uber Geek
+1 received by user: 482

Trusted

  Reply # 1682514 5-Dec-2016 14:02
Send private message

nicmair:

 

and an update, and lets call it the power of social media, and that someone from Chorus saw my post and thought, hell we can't let that happen.... :-)

 

 

 

but, get a phone call at midday, from Chorus, asking was I home, no, why, well we are booked to do your site inspection, so rather then say, hold it, its been rebooked for February, I said, give me 30min and I'll be there....  I get there, we have a chat for 10min about the how and what, I sign a few electronic forms and I ask so when are you going to do the actual install, he looks at me with a somewhat confused expression and says now....  so now I have two tech's here installing fibre.....

 

So I wonder what they will do in Feb :-)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

thats pretty awesome bro, nice xmas present :)





3310 posts

Uber Geek
+1 received by user: 681

Trusted

  Reply # 1686308 12-Dec-2016 07:57
Send private message

February - wow your lucky.

 

In hawkes bay I tell people you are likely to be waiting 6 months before its installed.





Ray Taylor
Taylor Broadband (rural hawkes bay)
www.ruralkiwi.com

There is no place like localhost
For my general guide to extending your wireless network Click Here




Mad Scientist
19823 posts

Uber Geek
+1 received by user: 2681

Trusted
Lifetime subscriber

  Reply # 1700419 9-Jan-2017 08:52
Send private message

nicmair:

 

So, last week I thought, what the heck, time to go to UFB....

 

 

 

Placed order through my ISP, so far so good..

 

Two days later got call from Chorus saying site inspection planned for today, that was quick I thought, cool.... that was delayed to Monday at 6ish last night, okay I thought, I can work with that, (was advised that delay was due to not enough tech's being available, not totally happy, but okay, whats couple of days).  Install was re booked for the 9th Dec.  So far so good....

 

Then just now get a call from VisionStream saying that due to Chorus dumping Downer and awarding the contract to VisionStream, they now can't do my install until 2nd February 2017, as they need to relocate tech's from Auckland to Dunedin!!!!

 

Now I'm okay with Chorus awarding the contract to whomever the want, but seriously no installs to Feb, and I suspect that this date will move, I just have little confidence it won't.

 

Come on Chorus, you should have managed the transition better then this and ensured Dunedin wasn't left with long delays like this!

 

So if you are in Dunedin, be prepared for a long wait for UFB.  So much for Gigatown....

 

 

 

Grumpy rant over :-)

 

 

 

 

 

  

 

 

They need to relocate techs from Auckland to all over the country?

 

1. How many techs do they have

 

2. How many places in the country did Downer used to service?

 

3. Why can't they just hire the existing Downer employees?

 

I'm asking because that sounds like Feb is just a cloud dream from what you're telling me!





Swype on iOS is detrimental to accurate typing. Apologies in advance.


2 posts

Wannabe Geek


  Reply # 1702298 12-Jan-2017 22:57
Send private message

Our cabinet area (Morrison St - Sidey St in Caversham) had the build finished the Monday before Christmas with the technicians on the street saying that the whole area is done and can be installed from tomorrow (Dec 21). Call my ISP they say the map says April 17 but put in a manual order. Get a call from them 2 days later saying Chorus rejected it on the grounds the area won't be finished with the physical build until Mar 31st.

 

 

 

Call Chorus and get the rudest customer rep saying the build will not be finished till Mar 31st and the technician (who had just finished working on the entire cabinet area) was wrong.

 

 

 

Planning to call Chorus again tomorrow and see what the hell is really happening now that the holiday season is over.

 

 

 

edit: spelling


919 posts

Ultimate Geek
+1 received by user: 224

Subscriber

  Reply # 1702454 13-Jan-2017 09:36
Send private message

Fuzzi99:

 

Our cabinet area (Morrison St - Sidey St in Caversham) had the build finished the Monday before Christmas with the technicians on the street saying that the whole area is done and can be installed from tomorrow (Dec 21). Call my ISP they say the map says April 17 but put in a manual order. Get a call from them 2 days later saying Chorus rejected it on the grounds the area won't be finished with the physical build until Mar 31st.

 

 

 

Call Chorus and get the rudest customer rep saying the build will not be finished till Mar 31st and the technician (who had just finished working on the entire cabinet area) was wrong.

 

 

 

Planning to call Chorus again tomorrow and see what the hell is really happening now that the holiday season is over.

 

 

Unfortunately this is normal. The Downer crew pack up and left my area at the beginning of July, I couldn't actually order the fibre until the 28th of August - I tried a manual order at the beginning of August and it got rejected.

 

Edit: Some good news for you (maybe) is the Chorus map kept saying "Available October" right up until the 28th of August when it suddenly became available (I was checking every day)


 1 | 2
View this topic in a long page with up to 500 replies per page Create new topic


Donate via Givealittle


Twitter »

Follow us to receive Twitter updates when new discussions are posted in our forums:



Follow us to receive Twitter updates when news items and blogs are posted in our frontpage:



Follow us to receive Twitter updates when tech item prices are listed in our price comparison site:





News »

Amazon introduces new Kindle with adjustable front light
Posted 21-Mar-2019 20:14


A call from the companies providing internet access for the great majority of New Zealanders, to the companies with the greatest influence over social media content
Posted 19-Mar-2019 15:21


Two e-scooter companies selected for Wellington trial
Posted 15-Mar-2019 17:33


GeForce GTX 1660 available now
Posted 15-Mar-2019 08:47


Artificial Intelligence to double the rate of innovation in New Zealand by 2021
Posted 13-Mar-2019 14:47


LG demonstrates smart home concepts at LG InnoFest
Posted 13-Mar-2019 14:45


New Zealanders buying more expensive smartphones
Posted 11-Mar-2019 09:52


2degrees Offers Amazon Prime Video to Broadband Customers
Posted 8-Mar-2019 14:10


D-Link ANZ launches D-Fend AC2600 Wi-Fi Router Protected by McAfee
Posted 7-Mar-2019 11:09


Slingshot commissions celebrities to design new modems
Posted 5-Mar-2019 08:58


Symantec Annual Threat Report reveals more ambitious, destructive and stealthy attacks
Posted 28-Feb-2019 10:14


FUJIFILM launches high performing X-T30
Posted 28-Feb-2019 09:40


Netflix is killing content piracy says research
Posted 28-Feb-2019 09:33


Trend Micro finds shifting threats require kiwis to rethink security priorities
Posted 28-Feb-2019 09:27


Mainfreight uses Spark IoT Asset Tracking service
Posted 28-Feb-2019 09:25



Geekzone Live »

Try automatic live updates from Geekzone directly in your browser, without refreshing the page, with Geekzone Live now.


Support Geekzone »

Our community of supporters help make Geekzone possible. Click the button below to join them.

Support Geezone on PressPatron



Are you subscribed to our RSS feed? You can download the latest headlines and summaries from our stories directly to your computer or smartphone by using a feed reader.

Alternatively, you can receive a daily email with Geekzone updates.