timmmay: I read on another thread that 70+ people in Wellington have been waiting a year or more for UFB, thanks to Wellington Electricity. Seems that legislation should've been passed to make this easier.
timmmay: Interesting. They were complaining about a month, I'm already at three months and I wouldn't surprise me if it actually took six months. Do I have to get my MP involved to get this done?
Fortunately my existing cable connection is pretty good so I'm not actually in a hurry, it's just frustrating as I've made changes to my internal network presuming UFB would be available in a reasonable timeframe.
On Thursday, Chorus notified Wellington Electricity of 60 sites where customers were waiting for connections.
Wellington Electricity will take three days to assess each site, then it may take up to three weeks before Chorus can begin making a connection. If poles need replacing it will take longer.
timmmay: 90 people and three days to assess is 180 days, if they have one person do it. Hopefully they're a bit smarter, and I assume they are, they have lots of contractors. My site is already assessed, they just need permission to do it.
I need to be there so they can test it and validate it, and I can't take time off work since I have a new job, back when we ordered it it'd have been fine.