Send private message

I guess Ms Curran's definition of catastrophic is slightly different from the general usage when a figure of eight cable has a single break and simply reroutes traffic via the rest of the ring.

Anyone lost any connectivity to OZ?

http://www.labour.org.nz/news/%E2%80%98catastrophic-failure%E2%80%99-hits-southern-cross-cable

A catastrophic failure has struck the Southern Cross international internet cable, says Labour’s Communications and IT spokesperson Clare Curran.

“Labour has learnt that a catastrophic failure at Southern Cross’s Alexandria landing station occurred this morning due to an unauthorised and un-notified software change to their wavelength switching platform at Alexandria, which blew up.

“We understand that partial service has been restored by reinstating old circuits via New Zealand. Full restoration is still being worked on.

“This shows the Government’s inaction and disregard for our international infrastructure could have equally catastrophic consequences for New Zealand.

“This is a crisis for New Zealand. Without international connectivity, our financial system and a large percentage of business would be severely affected.

“The Government must address the issue of international connectivity with urgency and provide a full assessment of the risks New Zealand faces through software failures and natural events on the single cable.

“Issues of capacity and affordability of data pale into insignificance when you consider the havoc that could be wrecked by a significant outage. This is a matter of grave importance for New Zealand.”

Filter this topic showing only the reply marked as answer View this topic in a long page with up to 500 replies per page Create new topic
 1 | 2 | 3
mercutio
1392 posts

Uber Geek


  #714709 9-Nov-2012 14:31
Send private message

i only heard of vocus losing connectivity. but it does seem more pointful to me than ufb.



BarTender
3606 posts

Uber Geek

ID Verified
Trusted
Lifetime subscriber

  #714714 9-Nov-2012 14:40
Send private message

But hang on a second wasn't Pacific Fibre only talking about doing a single circuit from AU-NZ-US?  No redundancy or second loop in that solution.  If they had managed to raise the $400Mil and built their cable then everyone between NZ & AU would be dead in the water.

Gotta be happy that SCCN DOES have redundant links, so even when a tech massively screws up they can still provide service.  Perhaps the 1.3Billion Investment SCCN made back in 1998 isn't that easy to replicate afterall.

mercutio
1392 posts

Uber Geek


  #714731 9-Nov-2012 15:06
Send private message

BarTender: But hang on a second wasn't Pacific Fibre only talking about doing a single circuit from AU-NZ-US?  No redundancy or second loop in that solution.  If they had managed to raise the $400Mil and built their cable then everyone between NZ & AU would be dead in the water.

Gotta be happy that SCCN DOES have redundant links, so even when a tech massively screws up they can still provide service.  Perhaps the 1.3Billion Investment SCCN made back in 1998 isn't that easy to replicate afterall.


providers can buy one patch on each cable though.




Oncop53
273 posts

Ultimate Geek


  #714734 9-Nov-2012 15:10
Send private message

Is there a more official source than the Labour party website?
Also what kind of legitimate software update would cause hardware to "blow up"? this must be delibrate, or else unbelievably incompetent.

ubergeeknz
3344 posts

Uber Geek

Trusted
Vocus

  #714737 9-Nov-2012 15:13
Send private message

I should imagine the terminating equipment they use is very specialised, and to a large degree is probably custom.  So it's quite conceivable.  But it sounds as if proper change control was not followed in this case, which is the more alarming part.

However, there is redundancy, because it's a loop (effectively).  But losing a direct link to AU will obviously drive up latency to AU sites.

This does highlight the case for a 2nd International fiber provider.  What if some critical piece of equipment at SouthernCross failed, which took out both links?

mercutio
1392 posts

Uber Geek


  #714738 9-Nov-2012 15:13
Send private message

Oncop53: Is there a more official source than the Labour party website?
Also what kind of legitimate software update would cause hardware to "blow up"? this must be delibrate, or else unbelievably incompetent.


http://www.nbr.co.nz/article/%E2%80%98catastrophic-failure-hits-southern-cross-cable-curran-ck-132090

unspecified
19 posts

Geek


  #714742 9-Nov-2012 15:19
Send private message

Umm... a what?

An "unauthorised and un-notified software change"?

Does this mean the 'cable operations software was hacked' or 'a tech changed something and got it wrong'?

Either is not good, but the first is worser.

I look forward to details.

 
 
 

Trade NZ and US shares and funds with Sharesies (affiliate link).
ajobbins
5052 posts

Uber Geek

Trusted

  #714747 9-Nov-2012 15:29
Send private message

What would have happened if the 'software patch' was applied to all of the wavelength switching platform gear across the whole SCCN?

Pac Fibre would at least add a second, independent supplier. If one or the other suppliers went totally offline, the other would (hopefully) still be up.




Twitter: ajobbins


ubergeeknz
3344 posts

Uber Geek

Trusted
Vocus

  #714770 9-Nov-2012 15:43
Send private message

ajobbins: What would have happened if the 'software patch' was applied to all of the wavelength switching platform gear across the whole SCCN?

Pac Fibre would at least add a second, independent supplier. If one or the other suppliers went totally offline, the other would (hopefully) still be up.


QFT.  And regardless of how much equipment redundancy there is within one supplier, these things can happen... Also, what if SCCF went bust, or got shut down for some other reason?  So much risk.

freitasm
BDFL - Memuneh
79308 posts

Uber Geek

Administrator
ID Verified
Trusted
Geekzone
Lifetime subscriber

  #714792 9-Nov-2012 16:17
Send private message

Oncop53: Is there a more official source than the Labour party website?


Just received from Southern Cross:


Contrary to a misleading and inaccurate media release from Labour’s Clare Curran, no ‘catastrophic failure’ has occurred on the Southern Cross Cable. 

The cable is, a figure of 8 network providing internet services to New Zealand, Australia, Pacific and the US.

In the early hours of this morning a limited outage affecting 10% of our active capacity occurred during our maintenance window which is a low traffic impacting period. 

The outage occurred at one of our Sydney cable stations, Alexandria, and it lasted from 3.17am – 4.28am, Sydney Time, impacting 4 of our customers. 

A problem occurred and the switch was reverted to its original software. 

The incident occurred as a part of authorised work taking place to expand capacity on the Southern Cross network.






Please support Geekzone by subscribing, or using one of our referral links: Quic Broadband (free setup code: R587125ERQ6VE) | Samsung | AliExpress | Wise | Sharesies | Hatch | GoodSync 


mercutio
1392 posts

Uber Geek


  #714795 9-Nov-2012 16:19
Send private message

freitasm:
Oncop53: Is there a more official source than the Labour party website?


Just received from Southern Cross:


Contrary to a misleading and inaccurate media release from Labour’s Clare Curran, no ‘catastrophic failure’ has occurred on the Southern Cross Cable. 

The cable is, a figure of 8 network providing internet services to New Zealand, Australia, Pacific and the US.

In the early hours of this morning a limited outage affecting 10% of our active capacity occurred during our maintenance window which is a low traffic impacting period. 

The outage occurred at one of our Sydney cable stations, Alexandria, and it lasted from 3.17am – 4.28am, Sydney Time, impacting 4 of our customers. 

A problem occurred and the switch was reverted to its original software. 

The incident occurred as a part of authorised work taking place to expand capacity on the Southern Cross network.




Then how come traceroute from telstra.net.au to vodafone was showing increased latency this morning (at reasonable hours).  Maybe Vocus had an outage of their own on top?

ubergeeknz
3344 posts

Uber Geek

Trusted
Vocus

  #714797 9-Nov-2012 16:21
Send private message

freitasm:
Oncop53: Is there a more official source than the Labour party website?


Just received from Southern Cross:


Contrary to a misleading and inaccurate media release from Labour’s Clare Curran, no ‘catastrophic failure’ has occurred on the Southern Cross Cable. 

The cable is, a figure of 8 network providing internet services to New Zealand, Australia, Pacific and the US.

In the early hours of this morning a limited outage affecting 10% of our active capacity occurred during our maintenance window which is a low traffic impacting period. 

The outage occurred at one of our Sydney cable stations, Alexandria, and it lasted from 3.17am – 4.28am, Sydney Time, impacting 4 of our customers. 

A problem occurred and the switch was reverted to its original software. 

The incident occurred as a part of authorised work taking place to expand capacity on the Southern Cross network.




That is a totally different story...

mercutio
1392 posts

Uber Geek


  #714798 9-Nov-2012 16:23
Send private message

ubergeeknz:
freitasm:
Oncop53: Is there a more official source than the Labour party website?


Just received from Southern Cross:


Contrary to a misleading and inaccurate media release from Labour’s Clare Curran, no ‘catastrophic failure’ has occurred on the Southern Cross Cable. 

The cable is, a figure of 8 network providing internet services to New Zealand, Australia, Pacific and the US.

In the early hours of this morning a limited outage affecting 10% of our active capacity occurred during our maintenance window which is a low traffic impacting period. 

The outage occurred at one of our Sydney cable stations, Alexandria, and it lasted from 3.17am – 4.28am, Sydney Time, impacting 4 of our customers. 

A problem occurred and the switch was reverted to its original software. 

The incident occurred as a part of authorised work taking place to expand capacity on the Southern Cross network.




That is a totally different story...


http://lists.ausnog.net/pipermail/ausnog/2012-November/015297.html

gzt

gzt
17157 posts

Uber Geek

Lifetime subscriber

  #714802 9-Nov-2012 16:37
Send private message

mercutio: http://lists.ausnog.net/pipermail/ausnog/2012-November/015297.html


Well that was interesting but I cannot say I understand it.

Does it contradict or support the official statement in any way?

mercutio
1392 posts

Uber Geek


  #714804 9-Nov-2012 16:39
Send private message

gzt:
mercutio: http://lists.ausnog.net/pipermail/ausnog/2012-November/015297.html


Well that was interesting but I cannot say I understand it.

Does it contradict the official statement in any way?


well it says it was unauthorised rather than routine.


 1 | 2 | 3
Filter this topic showing only the reply marked as answer View this topic in a long page with up to 500 replies per page Create new topic





News and reviews »

Air New Zealand Starts AI adoption with OpenAI
Posted 24-Jul-2025 16:00


eero Pro 7 Review
Posted 23-Jul-2025 12:07


BeeStation Plus Review
Posted 21-Jul-2025 14:21


eero Unveils New Wi-Fi 7 Products in New Zealand
Posted 21-Jul-2025 00:01


WiZ Introduces HDMI Sync Box and other Light Devices
Posted 20-Jul-2025 17:32


RedShield Enhances DDoS and Bot Attack Protection
Posted 20-Jul-2025 17:26


Seagate Ships 30TB Drives
Posted 17-Jul-2025 11:24


Oclean AirPump A10 Water Flosser Review
Posted 13-Jul-2025 11:05


Samsung Galaxy Z Fold7: Raising the Bar for Smartphones
Posted 10-Jul-2025 02:01


Samsung Galaxy Z Flip7 Brings New Edge-To-Edge FlexWindow
Posted 10-Jul-2025 02:01


Epson Launches New AM-C550Z WorkForce Enterprise printer
Posted 9-Jul-2025 18:22


Samsung Releases Smart Monitor M9
Posted 9-Jul-2025 17:46


Nearly Half of Older Kiwis Still Write their Passwords on Paper
Posted 9-Jul-2025 08:42


D-Link 4G+ Cat6 Wi-Fi 6 DWR-933M Mobile Hotspot Review
Posted 1-Jul-2025 11:34


Oppo A5 Series Launches With New Levels of Durability
Posted 30-Jun-2025 10:15









Geekzone Live »

Try automatic live updates from Geekzone directly in your browser, without refreshing the page, with Geekzone Live now.



Are you subscribed to our RSS feed? You can download the latest headlines and summaries from our stories directly to your computer or smartphone by using a feed reader.