So after getting our first UFB letter from chorus ("Your streets ahead") we now got the letter saying work will commence on our street (a small cul-de-sac in Balmoral, Auckland) on 11 June and all going well should be done around 20 June; very exciting!  But, I couldn't see an indication in the letter on whether this means UFB will be available after that date, or there's more waiting time after that?




"I was born not knowing and have had only a little time to change that here and there."         | Octopus Energy | Sharesies
              - Richard Feynman


Create new topic
lxsw20
3689 posts

Uber Geek
+1 received by user: 2174

Subscriber

  #1319248 8-Jun-2015 11:22
Send private message

Mine went live about a month after they put fibre on the poles. 



timmmay
20858 posts

Uber Geek
+1 received by user: 5349

Trusted
Lifetime subscriber

  #1319253 8-Jun-2015 11:24
Send private message

As I understand it, it probably takes a month or so after the fiber has been laid until it's available. However the process of getting it connected can take anything from 10 days to years, depending on your circumstances. A standard house should be easy, but in my case the telco had to get permission to use the power poles from Wellington Electricity, which took 8 months to resolve.

In summary, apply, but don't cancel your old connection until UFB is in and has been working for a couple of weeks. You'll pay a little more but Internet is almost a utility these days, going without is annoying.

sidefx

3775 posts

Uber Geek
+1 received by user: 1295

Trusted

  #1319274 8-Jun-2015 11:32
Send private message

Thanks guys. Yeah, it's a standard house though we're also renting, so hopefully shouldn't cause too many issues - I've already talked to Landlord about getting it installed, and after explaining the advantages of getting it done now he's almost as keen as me to get it installed.




"I was born not knowing and have had only a little time to change that here and there."         | Octopus Energy | Sharesies
              - Richard Feynman




TRONNZ
9 posts

Wannabe Geek
+1 received by user: 1


  #1319336 8-Jun-2015 12:42
Send private message

Fiber was installed in my area beginning of March 2015 (finished in my street and area). Site says 1st August 2015, contacted the Ultra-fast fiber guys and was told there is a 3 month wait/test period :(

Create new topic








Geekzone Live »

Try automatic live updates from Geekzone directly in your browser, without refreshing the page, with Geekzone Live now.



Are you subscribed to our RSS feed? You can download the latest headlines and summaries from our stories directly to your computer or smartphone by using a feed reader.