wasabi2k

2096 posts

Uber Geek


  #1108354 14-Aug-2014 13:06
Send private message

wellygary:
wasabi2k: Got my second letter - starting work today (14th August) Finishing by October 14.

I will ring Telecom/Spark tonight and see if there is any way to get lined up for a quick install.


Once they have finished the physical work, there is still another at least couple of weeks to provision the actual fibre from the local distributor to the individual drop points,

Once that is done they will allow ISPs to start signing up customers, then you have to go through the scoping and provision of fibre from the drop point to your house.

If you are lucky, you might have a live active conenction by the end of the year,  the final install to your house will take longer to happen than you think/want


Yeah not expecting to be live on the 15th of October - but will remain optimistic. Nothing but lawn from the kerb to our house - we own it, nothing shared.



hio77
12999 posts

Uber Geek

ID Verified
Trusted
Lizard Networks

  #1108439 14-Aug-2014 14:55
Send private message

Likely you will be set for a speedy install then once things are ready :)




#include <std_disclaimer>

 

Any comments made are personal opinion and do not reflect directly on the position my current or past employers may have.

 

 


wasabi2k

2096 posts

Uber Geek


  #1111058 19-Aug-2014 08:58
Send private message

Digger, Trench Covers and lots of trucks on our road and the next one up this morning....

IT'S HAPPENING.



wasabi2k

2096 posts

Uber Geek


  #1111882 20-Aug-2014 10:55
Send private message

Trucks outside our house this morning and lots of random holes in the ground.

Big drilling machine with a guy down the road with a box on the ground pointing - so suspect that is the directional drilling going on.

Bit truck with roll of green ducting at the top of the road too.

Poor guys out there in the pouring rain - at least the ground is soft.

04fuxake
64 posts

Master Geek


  #1115506 25-Aug-2014 21:18
Send private message

Got a postcard thing today from Vodafone saying that our street has UFB available now.  I remember seeing a handful of Chorus trucks up and down the street a month or two back.  Tempted to jump into UFB since it's cheaper UFB/VodafoneTV is cheaper than our current ADSL+/SKY combo.

wasabi2k

2096 posts

Uber Geek


  #1126499 11-Sep-2014 13:18
Send private message

Update 11/09:
Our road was finished a week ago - green ducts/cables sticking out by each house. They are working up the road around the corner, not sure how big an area they are doing.

Workers out yesterday repouring concrete paths (2 sections only) where they were damaged by the diggers - not a lot of damage to the street otherwise.

SOOOO EXCITED.

wasabi2k

2096 posts

Uber Geek


  #1126635 11-Sep-2014 16:52
Send private message

Spark chat person also pointed me here:
https://forms.smartmailpro.com/Telecom/FibreSubscription/fibre.aspx

to sign up for notification when Fibre is available at my address.

 
 
 

Cloud spending continues to surge globally, but most organisations haven’t made the changes necessary to maximise the value and cost-efficiency benefits of their cloud investments. Download the whitepaper From Overspend to Advantage now.
tdgeek
29740 posts

Uber Geek

Trusted
Lifetime subscriber

  #1126637 11-Sep-2014 16:58
Send private message

wasabi2k: Digger, Trench Covers and lots of trucks on our road and the next one up this morning....

IT'S HAPPENING.


Enable started laying 3 weeks ago, (ChCh) and Chorus ETA is November 2014, so thats a rough guide. They are around the corner right now, and a cable poking out of my partly dug up berm.  

matisyahu
1623 posts

Uber Geek

Trusted

  #1127661 13-Sep-2014 09:31
Send private message

wasabi2k: Got the Chorus letter today - UFB is coming to our street.

Stoked as we were originally by Jun-16, then Apr-15, now install is started.

I'm assuming it's roughly a 2-3 month process to get the street done?

I'm in Massey, West Auckland.

Looking forward to 100/30 or better.


I'm over in Avalon in Lower Hutt (close to Naenae college) and it wasn't scheduled until June 2016 but apparently they're starting the process already. The letter arrived in the mail on Friday so it'll be interesting to see what the time table is going to be - what is the usual time between receiving the letter and it actually being switched on/available for the masses?




"When the people are being beaten with a stick, they are not much happier if it is called 'the People's Stick'"


wasabi2k

2096 posts

Uber Geek


  #1148969 7-Oct-2014 10:37
Send private message

So our road has been "finished" for a while now.

1. The green ducts runs were sticking out at each house.
2. They were then buried and black caps sticking out of the ground.
3. Last weekend we had people coming round and putting grass seed and soil on the bits that were dug up.
4. Also had 2 segments of pavement relaid and finished which were damaged.
5. Seen a chorus van up the road with guy working in new trench/holes with covers on them. 

Due date is October 31 - I see they are working on surrounding roads so assume they do an entire area before making it available.

@kawaii - They started our road start of September and there is a sign by the work stating October 31 as the end date.

Having said that - that is when it is available to request - then you have to wait for scoping and install.

wasabi2k

2096 posts

Uber Geek


  #1164977 30-Oct-2014 12:47
Send private message

Update 30/10:
Most of the surrounding area looks to be done - completion date was meant to be tomorrow.

Spark website estimate is 30/11
Chorus Map estimate is Nov-2014

I've signed up for email alerts and will be checking the website so let's see.

mouarg
58 posts

Master Geek


  #1165018 30-Oct-2014 13:58
Send private message

I'm in the royal heights area as well but my street is still showing pale blue in the coverage maps. So depressing.

wasabi2k

2096 posts

Uber Geek


  #1165023 30-Oct-2014 14:13
Send private message

mouarg: I'm in the royal heights area as well but my street is still showing pale blue in the coverage maps. So depressing.


Yeah Granville Dr, Hassan Dr and HALF of Widmore all pale blue! 

Dynamic
3866 posts

Uber Geek

ID Verified
Trusted
Lifetime subscriber

  #1165038 30-Oct-2014 14:24
Send private message

I still want to hear from anyone in that area who gets UFB and has direct line of sight to the red secondhand furniture place on Triangle Road in front of Al's Mechanical (close to Western Lights pub).  Likely streets are Cedar Heights Ave, Benchmark Dr, Redwood Dr, Colwill Ave.




“Don't believe anything you read on the net. Except this. Well, including this, I suppose.” Douglas Adams

 

Referral links to services I use, really like, and may be rewarded if you sign up:
PocketSmith for budgeting and personal finance management.  A great Kiwi company.


wasabi2k

2096 posts

Uber Geek


  #1165043 30-Oct-2014 14:33
Send private message

Dynamic: I still want to hear from anyone in that area who gets UFB and has direct line of sight to the red secondhand furniture place on Triangle Road in front of Al's Mechanical (close to Western Lights pub).  Likely streets are Cedar Heights Ave, Benchmark Dr, Redwood Dr, Colwill Ave.


Yeah I'm downhill on the wrong side sorry.

1 | 2 | 3 | 4 | 5 | 6 | 7 | ... | 8
View this topic in a long page with up to 500 replies per page Create new topic





News and reviews »

Air New Zealand Starts AI adoption with OpenAI
Posted 24-Jul-2025 16:00


eero Pro 7 Review
Posted 23-Jul-2025 12:07


BeeStation Plus Review
Posted 21-Jul-2025 14:21


eero Unveils New Wi-Fi 7 Products in New Zealand
Posted 21-Jul-2025 00:01


WiZ Introduces HDMI Sync Box and other Light Devices
Posted 20-Jul-2025 17:32


RedShield Enhances DDoS and Bot Attack Protection
Posted 20-Jul-2025 17:26


Seagate Ships 30TB Drives
Posted 17-Jul-2025 11:24


Oclean AirPump A10 Water Flosser Review
Posted 13-Jul-2025 11:05


Samsung Galaxy Z Fold7: Raising the Bar for Smartphones
Posted 10-Jul-2025 02:01


Samsung Galaxy Z Flip7 Brings New Edge-To-Edge FlexWindow
Posted 10-Jul-2025 02:01


Epson Launches New AM-C550Z WorkForce Enterprise printer
Posted 9-Jul-2025 18:22


Samsung Releases Smart Monitor M9
Posted 9-Jul-2025 17:46


Nearly Half of Older Kiwis Still Write their Passwords on Paper
Posted 9-Jul-2025 08:42


D-Link 4G+ Cat6 Wi-Fi 6 DWR-933M Mobile Hotspot Review
Posted 1-Jul-2025 11:34


Oppo A5 Series Launches With New Levels of Durability
Posted 30-Jun-2025 10:15