# 177612 9-Aug-2015 03:36
Send private message

I placed an order through Spark on 18 July 2015 and here we are in August and no sign of anything happening; Wilson Hurst already has all the approval documentation and they're waiting on something to happen with Chorus? at this stage I'm very tempted to move if we're talking about over a month just to get fibre installed. Anyone give me a heads up on what is happening and why is it taking so long?




Laptop: MacBook Pro (15-inch, 2017)
Desktop: iMac (27-inch, 2017)
Smartphone: iPhone XS Max 256GB 'Space Grey'
Additional devices: Unifi Security Gateway, Unifi Switch, Unifi AP AC HD, Unifi Cloud Key, Apple Watch 4 44mm
Services: YouTube Premium, Wordpress, Skinny Mobile and Broadband

 


View this topic in a long page with up to 500 replies per page Create new topic
 1 | 2
672 posts

Ultimate Geek


  # 1361372 9-Aug-2015 04:38
One person supports this post
Send private message

Sounds like an MDU or shared property situation, In this case the consent is one of the longer things required but is certainly not the only thing that causes delays as it usually means a more complicated building/site with a plan that needs to be designed allowing connection of all parties involved (those same ones you had to get consent from) as well as generally more complicated work than would be involved to setup a single site on a single section.

You can always check with your ISP for confirmation on what status the order is in but unless chorus is waiting for the ISP to do something then you pretty much just have to ensure any required information is provided and sit and wait, The ISP can request a status update from chorus but cant really change the timings in any way other than the requested install dates which is more about the last step and finally livening up the service than anything before it.




Perpetually undecided.

8763 posts

Uber Geek

Lifetime subscriber

  # 1361381 9-Aug-2015 06:38
2 people support this post
Send private message

is your house stand alone, on a shared driveway, lease hold, attached to another house, or a multi dwelling unit?

if its any of the above bar the stand alone, then they require consent from any of the other parties involved in those situations. this may or may not happen, and it may or may not take some time.

Changing ISP's wont help, as the process with probably with chorus, and changing ISP's will cancel the order and you will have to start all over again.

why not call spark and ask them to give you an update on whats happening, and if they have no information, as them to get some from chorus.

 
 
 
 




1448 posts

Uber Geek

Subscriber

  # 1361383 9-Aug-2015 07:02
Send private message

As I've noted in the my original post:

"Wilson Hurst already has all the approval documentation"

The consent has already been put through for all those who I share the drive way with, it was put through the day I received confirmation. Wilson Hurst, the subcontractor, already has the approved documentation so they can go ahead but they're waiting on Chorus.




Laptop: MacBook Pro (15-inch, 2017)
Desktop: iMac (27-inch, 2017)
Smartphone: iPhone XS Max 256GB 'Space Grey'
Additional devices: Unifi Security Gateway, Unifi Switch, Unifi AP AC HD, Unifi Cloud Key, Apple Watch 4 44mm
Services: YouTube Premium, Wordpress, Skinny Mobile and Broadband

 


28130 posts

Uber Geek

Moderator
Trusted
Biddle Corp
Lifetime subscriber

  # 1361386 9-Aug-2015 07:19
Send private message

There isn't a simple answer to your question without knowing the complete details of your install. UFB installs take between 10 days to 9+ months.

Based on the fact you're a shared driveway you're a complex install. That means things can't happen within a short timeframe like a SDU install. I'd be expecting a timeframe somewhere within the vicinity of a few months assuming everything goes to plan.







2123 posts

Uber Geek


270 posts

Ultimate Geek


  # 1361418 9-Aug-2015 09:59
Send private message

My install is finally booked for Thursday next week, which will be 10 days short of 6 months.




 

832 posts

Ultimate Geek


  # 1361423 9-Aug-2015 10:13
Send private message

kawaii: As I've noted in the my original post:

"Wilson Hurst already has all the approval documentation"

The consent has already been put through for all those who I share the drive way with, it was put through the day I received confirmation. Wilson Hurst, the subcontractor, already has the approved documentation so they can go ahead but they're waiting on Chorus.


Isnt Wilson Hurst a property management Company? - if so they are wouldnt represent Chorus but have just gathered up the consents ?

 
 
 
 


3190 posts

Uber Geek


  # 1361431 9-Aug-2015 10:26
Send private message

Mine is a simple install, but keeps getting delayed for one reason or another. I thought 7 weeks was bad but maybe not so much now. Fingers crossed for tomorrow at last.




Always be yourself, unless you can be Batman, then always be the Batman



1609 posts

Uber Geek


  # 1361432 9-Aug-2015 10:30
Send private message

A simple install with no consent and no delay takes a month now, so don't expect anything done in a hurry.

929 posts

Ultimate Geek

Trusted
Chorus

  # 1361795 9-Aug-2015 23:03
One person supports this post
Send private message

kawaii: As I've noted in the my original post:

"Wilson Hurst already has all the approval documentation"

The consent has already been put through for all those who I share the drive way with, it was put through the day I received confirmation. Wilson Hurst, the subcontractor, already has the approved documentation so they can go ahead but they're waiting on Chorus.


Wilson Hurst is one of two companies contracted by Chorus to assist in the gaining of consents. All they do is work with the Chorus consent team to gain the required consents as quickly as possible. They are not a subcontractor and do not have any input in any other part of the fibre installation process.

What you must understand is that the physical signing and lodging of consent documents is only the start of the process for complex MDUs, rights of way, and cross leased properties.

Once consent is gained, your order is referred to the Chorus designers, whose job it is to design the fibre network from your boundary to ALL dwellings within your MDU, ROW or cross leased section. This can take anywhere from a week to a couple of months.

After the design is complete, depending on the complexity of the site it may require financial sign-off from Chorus and they may need time to get quotes prepared for the work. In some cases they may request a financial contribution from the property owner (such as a body corporate) This can take from a week to 3 months.

Once quoting is complete (if it was required) the job is assigned to the Chorus network build team. Their job is to actually begin the job of connecting your building (or buildings) to the main fibre cable in the street. This is the part that involves installing conduit underground on your property (if it is not an overhead feed). They will do this for ALL dwellings in your MDU/ROW/cross lease - even if not all dwellings have applied for service yet. Chorus typically allow around 30 working days (6 weeks) for build work to be completed, but it can take longer in some instances.

When build is complete, Chorus then need to update their records to show the new network in their system - this takes up to a week or so.

Only after all that is done, can they look that their technician schedule and book a date for your individual scope appointment and installation date. In some areas the techs are booked out by around a month, due to the volume of orders on the boil at any one time.

SO - essentially what I am trying to say is that even though the consents are all signed and lodged as the OP says, if every other subsequent stage takes the maximum amount of time, the OP could still be looking at a wait of over 7 months.

As others have suggested, your best bet is to contact Spark to request an update. They will in turn request an update from Chorus on your behalf, and will then contact you back when that update is received.




The views expressed by me are not necessarily those of my employer Chorus NZ Ltd




1448 posts

Uber Geek

Subscriber

  # 1361800 9-Aug-2015 23:15
Send private message

Wheelbarrow01:
kawaii: As I've noted in the my original post:

"Wilson Hurst already has all the approval documentation"

The consent has already been put through for all those who I share the drive way with, it was put through the day I received confirmation. Wilson Hurst, the subcontractor, already has the approved documentation so they can go ahead but they're waiting on Chorus.


Wilson Hurst is one of two companies contracted by Chorus to assist in the gaining of consents. All they do is work with the Chorus consent team to gain the required consents as quickly as possible. They are not a subcontractor and do not have any input in any other part of the fibre installation process.

What you must understand is that the physical signing and lodging of consent documents is only the start of the process for complex MDUs, rights of way, and cross leased properties.

Once consent is gained, your order is referred to the Chorus designers, whose job it is to design the fibre network from your boundary to ALL dwellings within your MDU, ROW or cross leased section. This can take anywhere from a week to a couple of months.

After the design is complete, depending on the complexity of the site it may require financial sign-off from Chorus and they may need time to get quotes prepared for the work. In some cases they may request a financial contribution from the property owner (such as a body corporate) This can take from a week to 3 months.

Once quoting is complete (if it was required) the job is assigned to the Chorus network build team. Their job is to actually begin the job of connecting your building (or buildings) to the main fibre cable in the street. This is the part that involves installing conduit underground on your property (if it is not an overhead feed). They will do this for ALL dwellings in your MDU/ROW/cross lease - even if not all dwellings have applied for service yet. Chorus typically allow around 30 working days (6 weeks) for build work to be completed, but it can take longer in some instances.

When build is complete, Chorus then need to update their records to show the new network in their system - this takes up to a week or so.

Only after all that is done, can they look that their technician schedule and book a date for your individual scope appointment and installation date. In some areas the techs are booked out by around a month, due to the volume of orders on the boil at any one time.

SO - essentially what I am trying to say is that even though the consents are all signed and lodged as the OP says, if every other subsequent stage takes the maximum amount of time, the OP could still be looking at a wait of over 7 months.

As others have suggested, your best bet is to contact Spark to request an update. They will in turn request an update from Chorus on your behalf, and will then contact you back when that update is received.


Geeze, with that amount of farting around I might as well cancel the installation - what a fiasco. Really, I can't believe that they have as many UFB users as they do given the amount of stuffing around involved with getting it installed.




Laptop: MacBook Pro (15-inch, 2017)
Desktop: iMac (27-inch, 2017)
Smartphone: iPhone XS Max 256GB 'Space Grey'
Additional devices: Unifi Security Gateway, Unifi Switch, Unifi AP AC HD, Unifi Cloud Key, Apple Watch 4 44mm
Services: YouTube Premium, Wordpress, Skinny Mobile and Broadband

 


1609 posts

Uber Geek


  # 1361802 9-Aug-2015 23:23
3 people support this post
Send private message

Building a brand new network for 3 million people takes time. You can't expect really expect such a big rollout to be done overnight. Once it is built though, the benefits would be worth it, gigabit connections for everyone and any future new connections could be done in minutes.

672 posts

Ultimate Geek


  # 1361803 9-Aug-2015 23:24
One person supports this post
Send private message

kawaii:
Wheelbarrow01:
kawaii: As I've noted in the my original post:

"Wilson Hurst already has all the approval documentation"

The consent has already been put through for all those who I share the drive way with, it was put through the day I received confirmation. Wilson Hurst, the subcontractor, already has the approved documentation so they can go ahead but they're waiting on Chorus.


Wilson Hurst is one of two companies contracted by Chorus to assist in the gaining of consents. All they do is work with the Chorus consent team to gain the required consents as quickly as possible. They are not a subcontractor and do not have any input in any other part of the fibre installation process.

What you must understand is that the physical signing and lodging of consent documents is only the start of the process for complex MDUs, rights of way, and cross leased properties.

Once consent is gained, your order is referred to the Chorus designers, whose job it is to design the fibre network from your boundary to ALL dwellings within your MDU, ROW or cross leased section. This can take anywhere from a week to a couple of months.

After the design is complete, depending on the complexity of the site it may require financial sign-off from Chorus and they may need time to get quotes prepared for the work. In some cases they may request a financial contribution from the property owner (such as a body corporate) This can take from a week to 3 months.

Once quoting is complete (if it was required) the job is assigned to the Chorus network build team. Their job is to actually begin the job of connecting your building (or buildings) to the main fibre cable in the street. This is the part that involves installing conduit underground on your property (if it is not an overhead feed). They will do this for ALL dwellings in your MDU/ROW/cross lease - even if not all dwellings have applied for service yet. Chorus typically allow around 30 working days (6 weeks) for build work to be completed, but it can take longer in some instances.

When build is complete, Chorus then need to update their records to show the new network in their system - this takes up to a week or so.

Only after all that is done, can they look that their technician schedule and book a date for your individual scope appointment and installation date. In some areas the techs are booked out by around a month, due to the volume of orders on the boil at any one time.

SO - essentially what I am trying to say is that even though the consents are all signed and lodged as the OP says, if every other subsequent stage takes the maximum amount of time, the OP could still be looking at a wait of over 7 months.

As others have suggested, your best bet is to contact Spark to request an update. They will in turn request an update from Chorus on your behalf, and will then contact you back when that update is received.


Geeze, with that amount of farting around I might as well cancel the installation - what a fiasco. Really, I can't believe that they have as many UFB users as they do given the amount of stuffing around involved with getting it installed.


While I don't suggest cancelling the install if you ever wish to have the service in future (it is only going to mean it takes longer when you change your mind)

I do agree that chorus do seem to have found a higher level of bureaucratic nonsense than any other LFC so far, All we see for it is a pile of excuses not found with the other LFC's.

I firmly believe we would not be seeing the majority of the issues we see today with chorus if other providers had gotten the contracts for the chorus assigned areas, It stems from nothing more than attempting to under cut any other contract without actually paying attention to what would be required to provide a competent level of service.




Perpetually undecided.

8763 posts

Uber Geek

Lifetime subscriber

  # 1361810 10-Aug-2015 06:20
Send private message

kawaii:Geeze, with that amount of farting around I might as well cancel the installation - what a fiasco. Really, I can't believe that they have as many UFB users as they do given the amount of stuffing around involved with getting it installed.


they are trying to build a system that lasts a long long time and isnt an eyesore likes in some countries

would you like something like this on every power pole?


Yes chours do seem to be taking their time but they have most of the country they have to roll the service out to.

1245 posts

Uber Geek


  # 1361826 10-Aug-2015 07:57
Send private message

Start to finish our MDU took about 2 years. The cabling/ducting into the common area of MDU was the hardest. After that is done it was about 2-3 months before ready for service

 1 | 2
View this topic in a long page with up to 500 replies per page Create new topic



Twitter and LinkedIn »



Follow us to receive Twitter updates when new discussions are posted in our forums:



Follow us to receive Twitter updates when news items and blogs are posted in our frontpage:



Follow us to receive Twitter updates when tech item prices are listed in our price comparison site:





News »

Intel expands 10th Gen Intel Core Mobile processor family
Posted 23-Aug-2019 10:22


Digital innovation drives new investment provider
Posted 23-Aug-2019 08:29


Catalyst Cloud becomes a Kubernetes Certified Service Provider (KCSP)
Posted 23-Aug-2019 08:21


New AI legaltech product launched in New Zealand
Posted 21-Aug-2019 17:01


Yubico launches first Lightning-compatible security key, the YubiKey 5Ci
Posted 21-Aug-2019 16:46


Disney+ streaming service confirmed launch in New Zealand
Posted 20-Aug-2019 09:29


Industry plan could create a billion dollar interactive games sector
Posted 19-Aug-2019 20:41


Personal cyber insurance a New Zealand first
Posted 19-Aug-2019 20:26


University of Waikato launches space for esports
Posted 19-Aug-2019 20:20


D-Link ANZ expands mydlink ecosystem with new mydlink Mini Wi-Fi Smart Plug
Posted 19-Aug-2019 20:14


Kiwi workers still falling victim to old cyber tricks
Posted 12-Aug-2019 20:47


Lightning Lab GovTech launches 2019 programme
Posted 12-Aug-2019 20:41


Epson launches portable laser projector
Posted 12-Aug-2019 20:27


Huawei launches new distributed HarmonyOS
Posted 12-Aug-2019 20:20


Lenovo introduces single-socket servers for edge and data-intensive workloads
Posted 9-Aug-2019 21:26



Geekzone Live »

Try automatic live updates from Geekzone directly in your browser, without refreshing the page, with Geekzone Live now.


Support Geekzone »

Our community of supporters help make Geekzone possible. Click the button below to join them.

Support Geezone on PressPatron



Are you subscribed to our RSS feed? You can download the latest headlines and summaries from our stories directly to your computer or smartphone by using a feed reader.

Alternatively, you can receive a daily email with Geekzone updates.