Benoire

2878 posts

Uber Geek
+1 received by user: 681


#319660 19-May-2025 09:59
Send private message

Morning folks

 

Chorus have come and disconnected our fibre fully to the roadside pillar to allow for external civil works.  I would like to lay a new conduit from the pillar to the new ETP location when the ground is dug up and prior to sub-base being laid.  What's the best spec conduit for the cable?  Anyone got any links to the correct laying methodology including how the conduit 'terminates' at the location for the ETP and roadside pillar?

 

I've got some time, demo is not starting until 1st week in June and concrete is not being laid until July/August but ideally I would like to get the conduit sorted early so I can flick back on fibre rather than stay on wireless for most of the works duration as the kids are already hating the idea of the 'slowness'!

 

Many thanks,

 

Chris


Create new topic

This is a filtered page: currently showing replies marked as answers. Click here to see full discussion.

BMarquis
466 posts

Ultimate Geek
+1 received by user: 581

Trusted
Chorus
Lifetime subscriber

  #3374597 19-May-2025 10:06
Send private message

Morning Chris!

You can purchase 20mm green lead-in pipe directly from an electrical wholesaler.
Making sure it comes with (or you also get) a draw-tape for our installer to use when re-connecting.

 


For some info on the what/how, there are some trenching guidelines here
https://www.chorus.co.nz/help/trenching-guidelines




Create new topic








Geekzone Live »

Try automatic live updates from Geekzone directly in your browser, without refreshing the page, with Geekzone Live now.



Are you subscribed to our RSS feed? You can download the latest headlines and summaries from our stories directly to your computer or smartphone by using a feed reader.