![]() ![]() ![]() |
|
graemeh:
I'd say do it in the following order:
1) Electrician and Plumber remove power outlets, switches, taps etc and leave them in a safe / non-leaking state
2) Demolition including removal of cabinets.
3) Builder builds stuff but leaves wall linings off
4) Electrician and Plumber re-arrange electrical and plumbing in wall (no outlets, switches taps etc installed yet)
5) Wall linings on, plastering/gib stopping done
6) Paint
7) Tile / floor coverings
8) Cabinets in
9) Take measurements for stone worktop, manufacture and install
10) Splashback in
11) Electrical and plumbing fittings installed
Done!
I'm assuming here that there will be some critical dimensions for the worktop so can only be made once the room is almost complete. If this is not the case it can be manufactured earlier and installed with the cabinets.
You may also need a building permit to do this so also need to allow for inspections in these tasks.
jonb: Thanks, that is just what I was wanting to get an idea of. Aiming to keep the existing tiled floor and use some spare tiles as needed.
Worktops will be installed about a week after cabinetry installation, with that in mind how far in advance should the strip-out occur to enable building, electrical plumbing and painting?
lissie:graemeh:
I'd say do it in the following order:
1) Electrician and Plumber remove power outlets, switches, taps etc and leave them in a safe / non-leaking state
2) Demolition including removal of cabinets.
3) Builder builds stuff but leaves wall linings off
4) Electrician and Plumber re-arrange electrical and plumbing in wall (no outlets, switches taps etc installed yet)
5) Wall linings on, plastering/gib stopping done
6) Paint
7) Tile / floor coverings
8) Cabinets in
9) Take measurements for stone worktop, manufacture and install
10) Splashback in
11) Electrical and plumbing fittings installed
Done!
I'm assuming here that there will be some critical dimensions for the worktop so can only be made once the room is almost complete. If this is not the case it can be manufactured earlier and installed with the cabinets.
You may also need a building permit to do this so also need to allow for inspections in these tasks.
We're currently at the gibbing stage - the plasterer starts tomorrow. We are laying vinyl plank and the installer is adamant that he is last - the cabinets are installed without the toe kicks and then he installs and the toe kicks go over the top.
We have 2 long benches (no corners) so the benchtops (one formica one SS) will be installed the same day as the cabinets.
The splashback will be measured for once the cabinets are in but the outlets will be attached before they return - it's no big deal to remove them again for the glass install apparently - and there is a 10 day delay for the glass The glass people will also install a temperorary backsplash behind the gas stove so the gasfitter can sign off.
graemeh:
I have a pet hate about floors that finish just under cabinets. It becomes a bit of a nuisance when fitting appliances like dishwashers. I can see why your flooring installer wants go last though. If it was me I'd have them lay the floor under any appliances like the dishwasher that sit on the floor.
In our house a previous owner had tiled after the dishwasher went in so you can guess what we needed to do when the dishwasher failed and had to be replaced!
|
![]() ![]() ![]() |