wally22:OK.
Make a bridge at right angles to the pipe that the bearer can rest on. If the horizontal piece of the bridge ends up below ground at all, use a pile(H5) for it.
Earlier you mentioned cutting piles. Always paint the cut ends with Metalex Concentrated Timber Preservative using appropriate safety precautions.
Alternatively and preferably, don't cut any piles. Some builders will happily cut piles and not treat the cut ends. The treatment is an envelope system so any break in the outside of the envelope should be retreated, but will not necessarily be as effective as the original commercial pressure treatment.
Shouldn’t be below ground level, but would be close. Using an H5 pile on its side as a bridge as you suggested is a good idea.
I was planning on on painting any cuts, but hadn’t looked up what product was required so thanks for that.