#317825 19-Nov-2024 08:34
Send private message

CNN is calling the UK's HS2 project the world's most expensive rail project per mile at US$200mil per mile.

 

Britain is building one of the world’s most expensive railways

 

Pfft! Auckland's CRL is currently budgeted at NZ$5.5billion for 3.4km so I make that approximately US$1.5bil per mile.

 

 


View this topic in a long page with up to 500 replies per page Create new topic
 1 | 2 | 3 | 4
Handsomedan
7155 posts

Uber Geek

ID Verified
Trusted
Subscriber

  #3310536 19-Nov-2024 08:44
Send private message

Can we also factor in the economic impact of the CRL, to show what it REALLY cost Auckland? 

And by that, I mean the reduction in business, the business failures as a result of the ongoing debacle etc





Handsome Dan Has Spoken.
Handsome Dan needs to stop adding three dots to every sentence...

 

Handsome Dan does not currently have a side hustle as the mascot for Yale 

 

 

 

*Gladly accepting donations...


 
 
 
 

Send money globally for less with Wise - one free transfer up to NZ$900 (affiliate link).
Asteros
188 posts

Master Geek


  #3310537 19-Nov-2024 08:45
Send private message

I agree the Auckland City Rail Link is probably the most expensive rail project per mile. I wonder why? The 18km Fehmarn Belt Road and Rail tunnel under the Baltic Sea between Germany and Denmark will cost $US8 Billion. Even if costs blow out it will be much cheaper than the Auckland project.


eracode
Smpl Mnmlst
8726 posts

Uber Geek

ID Verified
Trusted
Subscriber

  #3310540 19-Nov-2024 09:01
Send private message

Asteros:

 

I agree the Auckland City Rail Link is probably the most expensive rail project per mile. I wonder why? 

 

 

Because NZ.





Sometimes I just sit and think. Other times I just sit.




johno1234

2683 posts

Uber Geek


  #3310541 19-Nov-2024 09:01
Send private message

Handsomedan:

 

Can we also factor in the economic impact of the CRL, to show what it REALLY cost Auckland? 

And by that, I mean the reduction in business, the business failures as a result of the ongoing debacle etc

 

 

No sir, you are not going to tempt me down into that rabbit hole!

 

 


johno1234

2683 posts

Uber Geek


  #3310542 19-Nov-2024 09:03
Send private message

eracode:

 

Asteros:

 

I agree the Auckland City Rail Link is probably the most expensive rail project per mile. I wonder why? 

 

 

Because NZ.

 

 

Indeed. I think the costs of hiring a digger or an engineer here are comparable to the ROW. However the planning, consenting and compliance overheads appear to be a crushing burden on infrastructure projects.

 

 


wellygary
8201 posts

Uber Geek


  #3310554 19-Nov-2024 09:36
Send private message

Asteros:

 

I agree the Auckland City Rail Link is probably the most expensive rail project per mile. I wonder why? The 18km Fehmarn Belt Road and Rail tunnel under the Baltic Sea between Germany and Denmark will cost $US8 Billion. Even if costs blow out it will be much cheaper than the Auckland project.

 

 

Although it's got competition across the ditch 

 

Melbourne's 9km "metro" tunnel is costing $13.5 billion,AUD, that's ~$15 billion NZD for 9km, so that's on par with Auckland 

 

Melbourne= $1.7B / km, Auckland is $1.6B/km

 

https://www.theguardian.com/australia-news/2024/sep/26/melbourne-metro-tunnel-costs-launch-date-budget

 

 

 

 


gzt

gzt
16883 posts

Uber Geek

Lifetime subscriber

  #3310557 19-Nov-2024 09:43
Send private message

Asteros: I agree the Auckland City Rail Link is probably the most expensive rail project per mile. I wonder why? The 18km Fehmarn Belt Road and Rail tunnel under the Baltic Sea between Germany and Denmark will cost $US8 Billion.

 

Tunnels generally have one entry and one exit and that one is a relatively straight line. CRL has multiple passenger exits and follows contours in places.




Handsomedan
7155 posts

Uber Geek

ID Verified
Trusted
Subscriber

  #3310563 19-Nov-2024 10:02
Send private message

gzt:

 

Asteros: I agree the Auckland City Rail Link is probably the most expensive rail project per mile. I wonder why? The 18km Fehmarn Belt Road and Rail tunnel under the Baltic Sea between Germany and Denmark will cost $US8 Billion.

 

Tunnels generally have one entry and one exit and that one is a relatively straight line. CRL has multiple passenger exits and follows contours in places.

 


I remember when I was a child and the CRL had just started - maybe 50 years ago? - They said that the "cut and cover" tunnel system they were using was the cheapest, quickest and most effective way of doing this. 

Then they started boring holes in the bedrock. What ever happened to the "cut and cover" that they were originally supposed to be doing throughout the CBD? 





Handsome Dan Has Spoken.
Handsome Dan needs to stop adding three dots to every sentence...

 

Handsome Dan does not currently have a side hustle as the mascot for Yale 

 

 

 

*Gladly accepting donations...


johno1234

2683 posts

Uber Geek


  #3310565 19-Nov-2024 10:07
Send private message

Handsomedan:

 

Then they started boring holes in the bedrock. What ever happened to the "cut and cover" that they were originally supposed to be doing throughout the CBD? 

 

 

The first part from Britomart up Albert Rd was cut and cover.

 

 


Handsomedan
7155 posts

Uber Geek

ID Verified
Trusted
Subscriber

  #3310568 19-Nov-2024 10:20
Send private message

johno1234:

 

Handsomedan:

 

Then they started boring holes in the bedrock. What ever happened to the "cut and cover" that they were originally supposed to be doing throughout the CBD? 

 

 

The first part from Britomart up Albert Rd was cut and cover.

 

 

 


Yes, I remember that from my childhood. 





Handsome Dan Has Spoken.
Handsome Dan needs to stop adding three dots to every sentence...

 

Handsome Dan does not currently have a side hustle as the mascot for Yale 

 

 

 

*Gladly accepting donations...


wellygary
8201 posts

Uber Geek


  #3310572 19-Nov-2024 11:02
Send private message

Handsomedan:

 

Yes, I remember that from my childhood. 

 

 

Enabling works  for the cut and cover began in DECEMBER 2015!!!!!!!!!

 

https://www.mcconnelldowell.com/projects/city-rail-link-contract-2

 

 


richms
27959 posts

Uber Geek

Trusted
Lifetime subscriber

  #3310578 19-Nov-2024 11:17
Send private message

Its taking so long because they hire staff who stand around and do nothing all day. Like the road worker memes where one is digging and all the others are watching. Its a spectacle in nothing happening.





Richard rich.ms

johno1234

2683 posts

Uber Geek


  #3310590 19-Nov-2024 12:23
Send private message

richms:

 

Its taking so long because they hire staff who stand around and do nothing all day. Like the road worker memes where one is digging and all the others are watching. Its a spectacle in nothing happening.

 

 

They don't even watch these days. They're in the parked utes and trucks looking at their phones or sleeping. Apart from the one guy who drew the short straw on the stop-go sign.

 

 


Handsomedan
7155 posts

Uber Geek

ID Verified
Trusted
Subscriber

  #3310592 19-Nov-2024 12:40
Send private message

johno1234:

 

richms:

 

Its taking so long because they hire staff who stand around and do nothing all day. Like the road worker memes where one is digging and all the others are watching. Its a spectacle in nothing happening.

 

 

They don't even watch these days. They're in the parked utes and trucks looking at their phones or sleeping. Apart from the one guy who drew the short straw on the stop-go sign.

 

 

 


Come on...that's a bit disingenous. 

I distinctly remember seeing a guy watching from outside his ute once. 


Or maybe that's the Mandela effect...





Handsome Dan Has Spoken.
Handsome Dan needs to stop adding three dots to every sentence...

 

Handsome Dan does not currently have a side hustle as the mascot for Yale 

 

 

 

*Gladly accepting donations...


tripper1000
1602 posts

Uber Geek


  #3310631 19-Nov-2024 14:33
Send private message

One of the reasons it costs so much is because Kiwi's are/elect idiots who are allergic to city planning, which results in building things in the wrong order.

 

Drunken evolution instead of sensible planning and layout is happening right now out at Westgate.


 1 | 2 | 3 | 4
View this topic in a long page with up to 500 replies per page Create new topic





News and reviews »

New Suunto Run Available in Australia and New Zealand
Posted 13-May-2025 21:00


Cricut Maker 4 Review
Posted 12-May-2025 15:18


Dynabook Launches Ultra-Light Portégé Z40L-N Copilot+PC with Self-Replaceable Battery
Posted 8-May-2025 14:08


Shopify Sidekick Gets a Major Reasoning Upgrade, Plus Free Image Generation
Posted 8-May-2025 14:03


Microsoft Introduces New Surface Copilot+ PCs
Posted 8-May-2025 13:56


D-Link A/NZ launches DWR-933M 4G+ LTE Cat6 Wi-Fi 6 Mobile Hotspot
Posted 8-May-2025 13:49


Synology Expands DiskStation Lineup with DS1825+ and DS1525+
Posted 8-May-2025 13:44


JBL Releases Next Generation Flip 7 and Charge 6
Posted 8-May-2025 13:41


Arlo Unveils All-New PoE Adapter With Enhanced Connectivity
Posted 8-May-2025 13:36


Fujifilm Instax Mini 41 Review
Posted 2-May-2025 10:12


Synology DS925+ Review
Posted 23-Apr-2025 15:00


Synology Announces DiskStation DS925+ and DX525 Expansion Unit
Posted 23-Apr-2025 10:34


JBL Tour Pro 3 Review
Posted 22-Apr-2025 16:56


Samsung 9100 Pro NVMe SSD Review
Posted 11-Apr-2025 13:11


Motorola Announces New Mid-tier Phones moto g05 and g15
Posted 4-Apr-2025 00:00









Geekzone Live »

Try automatic live updates from Geekzone directly in your browser, without refreshing the page, with Geekzone Live now.



Are you subscribed to our RSS feed? You can download the latest headlines and summaries from our stories directly to your computer or smartphone by using a feed reader.







Backblaze unlimited backup