So 1 April UFB orderable in my street in Onehunga.
I ordered UFB via Voyager. Down a drive so needed consents, all fine with that.
17th June all consents in Chorus have sent me the docs and plans etc.
Voyager advise Chorus will be there 21 June.
21 June Chorus techs turn up, have no docs at all with them, I show them the Chorus docs "Haven't seen those before and they and we need to do it a different way" They measure a few things and disappear.
A day later am advised of a new install date 22nd July with a revised installation plan
19th July advised a new installation date 12th August
8th August advised a new installation date 2nd September.
Every time it has been "have a network issue and work outside your boundary is required."
Frustrated YES.
I don't blame Voyager.
Anyone got any suggestions on how to escalate this?