So after 5 weeks of waiting I'm told that Spark"now working on gaining consent from the power company/council to utilise their power pole for your installation"...
Mt Cook, Wellington, New Zealand
![]() ![]() ![]() |
|
Five weeks is nothing, it took 8 months in the northern suburbs, though I was one of the earliest UFB users in the area. You have no choice but to be patient, it happens when it happens.
They need to send techs to inspect each pole and make sure it is safe to climb, attach additional cables to it, etc. So can't be blanket approval.
And there is at least one story on here of a person having had consent to use the pole refused. Be aware.
I'm in Mt Cook as well and was only held up for about four months, but this was back in 2014 when they were just getting their act together at WE to create a consenting process with Chorus.
Most poles are owned by the applicable power company, but some are on private land and therefore can be owned by that landowner. Some poles are found to be unsafe during scoping and require replacement before the techs are allowed to scale them.
All poles are subject to a maximum load, therefore blanket consent is not viable. Consent for individual installations must be obtained with thought given to the total load on the pole.
I don't know why some take a long time to get consent and others don't. From my experience Wellington Electricity seem to take the longest in the country. (and seem to have the most rotten poles which require replacement).
The views expressed by me are not necessarily those of my employer Chorus NZ Ltd
Horizon (Bay of Plenty) either offers blanket consent or has a very fast turnaround; the installer came in the morning, realised that they needed to use the pole, and then came back the same afternoon to install it.
Vector has a system where suspect poles are tagged, which may not speed things up but does identify that a particular pole is not allowed to have a ladder lent against it. There have been cases where normal looking poles have fallen over when a tech goes up the ladder.
There are also issues about what fibre is allowed to be run on aerial installs (consents may limit to a single cable that may be replaced but not added to). Since Chorus is supposed to keep the copper intact unless there is no choice, some of jobs may require special composite fibre/copper cable to be specified at the scoping stage and alternatives investigated such as attaching to fence lines.
Time to find a new industry!
Looking at the absolute crap weather blowing around Wellington today, it's not surprising that they take a conservative approach re: extra wires strung from power poles.
zhzh: So after 5 weeks of waiting I'm told that Spark"now working on gaining consent from the power company/council to utilise their power pole for your installation"...
Mt Cook, Wellington, New Zealand
Issues with poles can be a nightmare. It's why Chorus have tried to minimise use of any WE poles in their build.
Once lodged assuming the pole isn't red flagged consent will normally take 2-3 weeks.
froob: Such a strange contrast to my install - also aerial, also Wellington - literally one week from ordering to completion. Not trying to gloat, just genuinely confused how the experiences could be so different. Why is the consent not obtained as part of the network build in anticipation of individual connection requests? Surely that should be a consideration in the network design, particularly if the consent can actually be refused?
I'll make an assumption with a 1 week build time that your connection uses a Chorus pole and not a WE one.
sbiddle:
I'll make an assumption with a 1 week build time that your connection uses a Chorus pole and not a WE one.
The whole install was done on the initial scoping visit, so I would think that was right. Either that, or consent had already been obtained. Chorus has its fibre "black box" located on the pole, and the aerial cable is a single span from there to my house. (Power and HFC also are delivered from the same pole.)
froob:
sbiddle:
I'll make an assumption with a 1 week build time that your connection uses a Chorus pole and not a WE one.
The whole install was done on the initial scoping visit, so I would think that was right. Either that, or consent had already been obtained. Chorus has its fibre "black box" located on the pole, and the aerial cable is a single span from there to my house. (Power and HFC also are delivered from the same pole.)
The pole across the road, which is a timber one, has got fibre box on it.
The pole on my side, a concrete one, is the one needs consent. So it is a WE one?
zhzh:
froob:
sbiddle:
I'll make an assumption with a 1 week build time that your connection uses a Chorus pole and not a WE one.
The whole install was done on the initial scoping visit, so I would think that was right. Either that, or consent had already been obtained. Chorus has its fibre "black box" located on the pole, and the aerial cable is a single span from there to my house. (Power and HFC also are delivered from the same pole.)
The pole across the road, which is a timber one, has got fibre box on it.
The pole on my side, a concrete one, is the one needs consent. So it is a WE one?
Very likely.
Chorus poles only have Chorus services on them, but I have seen a couple that have VF HFC services running from them as part of the overlead lead-in to avoid an aerial tresspass. Concrete polls are WE and will have power as well as VF HFC services on them.
zhzh: So after 5 weeks of waiting I'm told that Spark"now working on gaining consent from the power company/council to utilise their power pole for your installation"...
Mt Cook, Wellington, New Zealand
as other have said, grab a book and get comfortable, this might take a while.
The problem i had was incompetent scoping. When each team came to do something they discovered a problem that hadn't been noted during scoping. Instead of all the problems being fixed at the same time, they got fixed one after another.
7 months for me.
worth it in the end .....
Most of the posters in this thread are just like chimpanzees on MDMA, full of feelings of bonhomie, joy, and optimism. Fred99 8/4/21
|
![]() ![]() ![]() |